5E Advanced Materials (FEAM) Q1 2027 earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2027 earnings summary
17 Nov, 2026Executive summary
October 1 Searles Valley acquisition shifted operations from development stage to producing borates and industrial minerals; acquired results were excluded from Q1.
Acquired platform includes three processing sites, 54 MW cogeneration, the Trona Railway, a water utility, ~25,000 acres, mineral tenure across >9,000 acres and ~250 employees.
Q1 net loss widened to $13.1M from $10.7M; cash was $15.6M, and substantial doubt about going concern remains.
Near-term priorities include integration, production reliability, V-BOR sales and output growth, cost resets, SAC restart and greater cogeneration use.
Financial highlights
Q1 operating expenses rose 24% YoY to $13.3M; operating loss was $13.3M versus $10.7M.
G&A increased 85% to $6.4M, including $4.2M acquisition-related legal and due diligence costs; project expenses fell 14% and SSF costs fell 28%.
Operating cash outflow was $3.4M, investing outflow $0.3M and financing outflow $0.1M; cash declined $3.8M in the quarter.
October V-BOR production was 6,200 tons and sales ~2,500 tons, against starting inventory of ~3,000 tons; netback was ~$767 per ton.
Outlook and guidance
V-BOR annualized output was ~82,000 short tons, with a target to recover toward ~100,000; November production target was ~8,300 tons as sales ramped with export logistics.
SAC restart was targeted for January; idle Trona boric acid production was also planned to restart.
Cogeneration and a capacitor installation target $8M–$9M annual net operating cost savings; capacitor cost is ~$500,000, with reduced grid reliance targeted by next summer.
A 205-well drilling and workover program aims to improve brine grade; October grade was in line with modeled expectations.
Fort Cady commercial production was previously targeted for 2030, subject to FEED progress by January 2027 and financing for construction targeted to start in January 2028.
Latest events from 5E Advanced Materials
- Board backs five director nominees and all three proposals at the Dec. 7, 2026 meeting.FEAM
Proxy filing - Board seeks approval for a 2.5M-share plan expansion as overhang could reach 7.0%.FEAM
Proxy filing - Searles adds U.S. boron production and growth options alongside Fort Cady.FEAM
M&A announcement - Transformative acquisition creates a leading U.S. boron producer with immediate revenue and scale.FEAM
Water Tower Research Virtual Insights Conference - Updated feasibility study shows strong project economics, but continued operations depend on new financing.FEAM
Q4 2026 - Fort Cady leverages rare boron deposits, flexible operations, and diverse revenue streams for growth.FEAM
Fireside chat - Advancing a de-risked, fully permitted U.S. boron project toward commercial scale and value realization.FEAM
Investor presentation - California boron project advances amid tight supply, rising prices, and key offtake talks.FEAM
Planet MicroCap Las Vegas 2026 - Major offtake signed, strong pipeline, and new products drive progress toward project financing.FEAM
Investor update