4 Aug, 2026Strategic positioning and investment plan
Owns 51% of Greece’s sole electricity transmission operator, providing pure-play exposure to a critical infrastructure asset with regulated, predictable revenues.
Plans up to €530m capital increase to participate in IPTO’s €1bn equity raise, supporting a €6bn capex plan for 2026–2029.
Focused on doubling regulated asset base (RAB) from €3.3bn in 2025 to ~€7bn by 2029, with ~20% CAGR, among the fastest in Europe.
Investment priorities include major island interconnections, mainland grid reinforcement, and new international links.
Hellenic Republic committed to pro-rata participation and backstop in the capital increase.
Regulatory and financial framework
Operates under an independent, EU-aligned regulatory regime with ex-ante revenue cap and RAB-based model.
Allowed pre-tax WACC set at 6.87% for 2026, with inflation-linked, predictable returns and insulation from macro volatility.
Regulatory framework supports capex and performance, with best-in-class risk-adjusted returns versus European peers.
RAB compounding and optimized leverage expected to drive post-tax RoE from 8.5% in 2025 to ~11% in 2029.
Target capital structure maintains strong investment grade profile, with net debt/RAB below 60% and FFO/net debt above 10%.
Operational excellence and growth delivery
Demonstrated track record of delivering complex, sector-first projects and maintaining high grid availability.
Rapid integration of renewables, with 4.3 GW new RES connected in 2024–2025 while ensuring grid stability.
Zero systemic failures in 2025, advanced digital monitoring, and strong ESG performance, including high taxonomy alignment and no environmental fines.
Experienced management team and skilled workforce, with proactive hiring and training to support capex ramp-up.
Operational cash flow, EU/national subsidies, and prudent leverage underpin funding for the investment cycle.
Latest events from Admie Holding
- Strong Q1 profit and revenue growth driven by grid investments and interconnection projects.ADMIE
Q1 202426 Jun 2026 - Net profit up 27% to €37.1m, liquidity surges, and interim dividend of €13.5m approved.ADMIE
Q2 202426 Jun 2026 - Revenue and profit rose over 31% year-over-year, with robust grid investments and dividend payout.ADMIE
Q3 202426 Jun 2026 - Strong revenue and profit growth in 2024, driven by grid investments and renewables integration.ADMIE
Q4 202426 Jun 2026 - Revenue and net profit rose 2%, with major grid projects and new bond financing advancing.ADMIE
Q1 202526 Jun 2026 - Net profit fell to €34.1m, but liquidity, capex, and project pipeline strengthened.ADMIE
Q2 202526 Jun 2026 - Net profit and revenue declined, but capex and dividends rose amid major grid projects.ADMIE
Q3 202526 Jun 2026 - Revenue and profit declined, but key interconnection projects and renewables advanced.ADMIE
Q4 202526 Jun 2026 - Robust Q1 2026 growth in revenue and profit, with major investments and regulatory milestones.ADMIE
Q1 202626 Jun 2026