5 Oct, 2026Executive summary
The remaining 48.92% stake in AFYREN NEOXY was acquired for €11.3m, bringing ownership to 100%; full consolidation from 31 March 2026 limits comparison with H1 2025.
H1 net income was €2.429m, including €15.816m of non-recurring acquisition-related income; pro forma net income was a €1.0m loss.
Production ramp-up and plant performance investments remain central to reaching plant, then consolidated, break-even.
Financial highlights
H1 revenue was €1.265m versus €1.204m in H1 2025; it included €585k from acid and fertilizer sales and €680k from services.
Current operating loss was €9.650m; pro forma current operating loss, including AFYREN NEOXY from 1 January, was €15.6m.
Operating income was €6.166m, including €15.816m of non-current income tied mainly to acquisition accounting and revaluation of the previously held stake.
Net income was €2.429m versus a €6.924m loss in H1 2025; basic and diluted EPS were €0.06 versus -€0.27.
Plant billings were ~€1m in H1, twice the full-year 2025 level; consolidated results included plant product revenue for the first time.
Outlook and guidance
H2 2026 AFYREN NEOXY revenue is targeted to double versus H1, mainly through higher production; planned shutdowns are incorporated as optimisation continues through 2027.
The priority is removing bottlenecks and reaching plant, then consolidated, break-even after the 2026–2027 investment programme.
Plant 2 investment could be considered in 2028, with commissioning targeted for 2030, subject to confirmation of the break-even trajectory.
Advanced projects in France and Thailand target annual capacities of 24,000 and 28,000 tonnes, respectively, with profitability targeted above the current plant through scale effects.
Latest events from AFYREN
- First sales achieved; continuous production and scale-up remain the 2025 inflection point.ALAFY
H2 2024 - Production ramp-up delays weigh on H1 results; 2025 break-even remains the target.ALAFY
H1 2024 - Industrial production is proven; ramp-up, funding and execution now determine the path to break-even.ALAFY
H2 2025 - Continuous production began as H1 losses widened ahead of the H2 sales ramp-up.ALAFY
H1 2025