AIB Data Centers (AIB) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
21 Oct, 2026Platform and contracted capacity
Develops 40–90 MW data centers for AI and HPC customers, securing contracted utility power before committing development capital.
Contracted utility power totals ~120 MW across five named sites in four U.S. metro markets; CLT1 has 50 MW of contracted critical IT capacity.
The model owns and operates buildings, power infrastructure and cooling; customers own and operate the servers and GPUs.
Market demand and power scarcity
Third-party forecasts put global data center power demand at 82 GW in 2025 and ~220 GW by 2030, with ~70% of 2030 demand expected to be AI-related.
Global data center electricity use is forecast at 945 TWh by 2030 versus 415 TWh in 2024; cumulative investment needs exceed $1.7T through 2030.
Q1 2026 vacancy was 0.3% in Northern Virginia, 1.0% in Atlanta, 1.8% in Dallas–Fort Worth and 2.2% in Chicago; new grid connections average 4+ years.
88% of Dallas–Fort Worth capacity under construction was pre-leased; grid, equipment and permitting constraints vary by market.
Development model and execution
The sequence is to secure power and site control, contract customer capacity, arrange project funding, build in phases and generate long-term contracted revenue.
Utility agreements, customer prepayments, project-level debt and preferred equity are intended to fund development; phased construction can bring initial halls into service before full-site completion.
In the 12 months to September 2026, milestones included the first utility agreement, ~120 MW of contracted utility power and the first long-term customer agreement.
Two 25 MW CLT1 data halls were expected for delivery in Q4 2027; timing is estimated and depends on utility service, construction, procurement, permitting and financing.
Latest events from AIB Data Centers
- Nebius’s 12-year CLT1 contract anchors a 120 MW pipeline and project-level funding plan.AIB
Investor update - A 50 MW Nebius lease anchors a power-secured, 280 MW expansion pipeline.AIB
LD Micro 20th Annual Main Event Conference - A 50 MW Nebius lease anchors an ~$800m build without a planned equity raise.AIB
Investor update - Signed a 12-year, 50 MW anchor contract, launching CLT1 in Oct 2026 with strong revenue outlook.AIB
Investor presentation - Power-first approach and rapid execution target surging AI data center demand with strong growth pipeline.AIB
IAccess Alpha Virtual Best Ideas Fall Investment Conference 2026 - Power-secured AI data center platform with 65 MW contracted, 570 MW pipeline, and strong liquidity.AIB
Investor presentation - Power-first strategy and strong pipeline position for rapid AI/HPC data center growth.AIB
Emerging Growth Conference - Rapidly scaling AI data center platform leverages power-first strategy amid sector supply constraints.AIB
Investor presentation - Q2 revenue dropped 39% as operations shifted to AI/HPC; cash rose to $52.8M, net loss was $3.5M.AIB
Q2 2026