AIC Mines (A1M) Q1 2027 earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2027 earnings summary
22 Oct, 2026Executive summary
Produced 3,072t of copper and 1,562oz of gold in concentrate; record quarterly net mine cash flow of $33.4m after $7.9m of capital investment.
Jericho stoping began ahead of schedule, commissioning of the expanded 1.1Mtpa Eloise plant started early, and binding agreements were signed to acquire Mt Cuthbert.
Financial highlights
September-quarter metal sales net of TC/RC were $69.6m; operating mine cash flow was $41.3m and net mine cash flow was $33.4m.
Eloise sold 3,078t of copper at a realized price of A$19,648/t; sales benefited from concentrate inventory built during the prior quarter.
Jericho generated $8.0m in metal sales and a $5.8m cash margin, treated as pre-commercial and credited to project capital.
Cash at bank was $37.2m at quarter-end, down from $41.7m at 30 June 2026.
Eloise expansion capital was largely spent, with $1m remaining; aggregate spend was within $1m of guidance.
Outlook and guidance
FY27 guidance maintained at 17,500–18,500t copper and 7,250–7,750oz gold; AISC guidance is $4.80–$5.20/lb and AIC $5.20–$5.60/lb.
December-quarter guidance is 4,500–4,900t copper and 2,000oz gold; management targets the midpoint despite September production below plan, with high-grade ore potentially supporting the top end.
Jericho targets initial production of ~37,000t/month and commercial production from January 2027, when its operating results will be consolidated with Eloise.
Expanded Eloise plant completion remains scheduled for December 2026 and on budget; commissioning is progressing through a 4–12 week rocks-through-equipment phase.
Mt Cuthbert acquisition and placement require shareholder approval at an EGM scheduled for 4 November 2026.
Latest events from AIC Mines
- Production growth at Eloise and Jericho targets 27,000t Cu by FY29, backed by strong reserves.A1M
Corporate presentation - Revenue and profit surged on strong copper prices, with major investment in plant expansion and new climate disclosures.A1M
H2 2026 - Production to double, plant expansion and exploration success drive robust copper growth strategy.A1M
Noosa Mining Conference 2026 - Copper output to reach 25,000–27,000t by FY29 as 1.5Mtpa expansion accelerates.A1M
Guidance - Met FY26 copper guidance, maintained strong cash flow, and advanced key growth projects.A1M
Q4 2026 - Eloise and Jericho drive record copper resources, production growth, and disciplined expansion.A1M
Investor presentation - Record cash flow and production, expansion on track, costs below guidance despite diesel volatility.A1M
Q3 2026 - Revenue and profit rose sharply in FY25, funding major growth at Jericho and Eloise.A1M
H2 2025 - Record output, robust cash flow, and major expansion progress despite weather impacts.A1M
Q2 2026