Alamos Gold (AGI) Q2 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2025 earnings summary
17 Apr, 2026Executive summary
Gold production rose 10% sequentially in Q2 2025 to 137,200 ounces, with all operations contributing and record revenues of $438.2 million; free cash flow reached $85 million, and the company remains on track to meet full-year production guidance despite increased costs.
Completed Argonaut Gold acquisition in July 2024, expanding the Island Gold District and contributing to consolidated results.
Major growth projects, including Island Gold Phase 3+ Expansion and Lynn Lake, are progressing, with 79% of Island Gold expansion capital spent or committed and ore processing transitioned to the Magino mill.
The company expects further production growth and margin expansion in H2 2025, supported by ongoing expansion projects.
Financial highlights
Q2 2025 revenues reached a record $438.2 million, up 32% year-over-year, with net earnings of $159.4 million ($0.38/share) and adjusted net earnings of $144.1 million ($0.34/share).
Operating cash flow before working capital changes was $233 million; free cash flow was $85 million, reversing negative free cash flow in Q1.
Cash and cash equivalents at quarter-end were $344.9 million, with total liquidity of $844.9 million.
Returned $21 million to shareholders via share repurchases and dividends.
Realized gold price averaged $3,223/oz, up 38% year-over-year.
Outlook and guidance
Full-year 2025 production guidance maintained at 580,000–630,000 ounces; AISC guidance raised by 12% to $1,400–$1,450/oz due to higher share-based compensation, royalty expenses, and slower starts at Magino and Young-Davidson.
Costs are expected to decline in H2 2025 as production ramps up and operational improvements take effect.
Longer-term production is expected to reach 1 million ounces annually by 2028, driven by Island Gold and Lynn Lake expansions.
Lynn Lake project delayed by six months due to wildfires; completion now expected in H2 2028.
Latest events from Alamos Gold
- Record gold output and revenue, led by Magino, drive strong cash flow and growth outlook.AGI
Q3 202417 Apr 2026 - Record gold output, lower costs, and Magino integration drove record free cash flow and revenue.AGI
Q2 202417 Apr 2026 - Q1 2025 saw strong revenue growth and project progress, with cost reductions expected ahead.AGI
Q1 202517 Apr 2026 - Record Q3 free cash flow and revenue set the stage for strong growth despite operational setbacks.AGI
Q3 202517 Apr 2026 - Gold production and free cash flow set to surge with major expansions and disciplined growth.AGI
Corporate presentation13 Apr 2026 - Gold production to surpass 1M ounces by 2029, with costs declining and reserves expanding.AGI
35th BMO Global Metals, Mining & Critical Minerals Conference27 Feb 2026 - Record revenues and free cash flow drive 60% dividend hike and major growth plans.AGI
Q4 202519 Feb 2026 - Path to 1M oz gold by 2029–2030, with lower costs, robust cash flow, and major expansions.AGI
Investor Day 20264 Feb 2026 - Clear path to 1M+ ounces annual gold output and sector-leading growth through 2030.AGI
The 15th Annual East Coast IDEAS Conference3 Feb 2026