16 copper-gold concentrate shipments totaling 3,061 MT copper and 78.6 kg gold dispatched since operations began at Al Wash-hi Majaza plant.
Interim replacement filter presses arrived, with commissioning scheduled for late June 2025 to address production bottlenecks.
Promising exploration and gravity survey results at Block 8, with a high-priority anomaly (H1) identified for further drilling.
Royal Decree issued for Block 22B Concession in March, enabling new exploration planning.
Rights issue discontinued due to regulatory proceedings, impacting capital allocation for equipment orders.
Financial highlights
$15.46 million in receipts from customers for the quarter, $35.20 million year-to-date.
$11.63 million spent on mining production and development activities during the quarter.
Net cash used in operating activities was $2.90 million for the quarter, with $2.71 million net cash from operations year-to-date.
Cash and cash equivalents at quarter end were $11.47 million.
Aggregate payments to related parties totaled $151,000 for directors’ remuneration.
Outlook and guidance
Continued copper-gold concentrate production at Al Wash-hi Majaza plant expected.
Installation and commissioning of new tailings filter presses targeted for completion by end of June 2025.
Interim drilling results for Al Wash-hi mining licence expansion and infill program anticipated.
Exploration to commence at Block 22B and progress at Block 8, with updates expected.
Grant of mining license over Daris 3A5 prospect expected during 2025.
Latest events from Alara Resources
- Above-plan copper production and resource growth support a pathway to mid-tier producer status.AUQ
Investor presentation21 Apr 2026 - First copper-gold shipments and expanded exploration mark a transformative year amid ramp-up costs.AUQ
H2 20241 Apr 2026 - Revenue up sharply on copper sales, but net loss and working capital deficit persist.AUQ
H2 20251 Apr 2026 - Revenue surged 194% and net profit rebounded, driven by record mine output and efficiency gains.AUQ
H1 202616 Mar 2026 - Rising copper demand and robust Omani operations position the company for long-term growth.AUQ
Investor presentation11 Mar 2026 - Copper concentrate production rose 10% and cash reserves reached A$7.79 million.AUQ
Q1 2026 TU21 Dec 2025 - Production and exploration advanced, cash position strengthened, and key licenses awaited.AUQ
Q4 2025 TU1 Oct 2025 - Alara Resources advances copper production, launches major capital raise, and targets growth in Oman.AUQ
AGM 202413 Jun 2025 - Production and process improvements at Wash-hi Majaza mine drive higher copper output and efficiency.AUQ
Q1 2025 TU13 Jun 2025