22 Jun, 2025Executive summary
Installation of two new Tailings Filter Presses (TFPs) underway to improve tailings processing and increase recovery rates to 90-92%.
Monthly copper concentrate production expected to rise to 3200-3400 WMT, reaching 90-92% of plant capacity after TFP commissioning.
Full plant capacity of 3500-3600 WMT per month targeted after long-term TFP solution.
Financial highlights
Substantial rise in production-related payments in the March 2025 quarter compared to the previous quarter, mainly due to resumed mining operations and supplier invoice settlements.
Increased expenses also driven by purchases of critical consumables and spare parts for ongoing operations.
Outlook and guidance
Similar expenditure patterns expected to continue as mining operations have stabilized following the ramp-up phase.
Further updates on TFP replacement outcomes to be provided once commissioning commences.
Latest events from Alara Resources
- Revenue surged 194% and net profit rebounded, driven by record mine output and efficiency gains.AUQ
H1 202616 Mar 2026 - Rising copper demand and robust Omani operations position the company for long-term growth.AUQ
Investor presentation11 Mar 2026 - Copper concentrate production rose 10% and cash reserves reached A$7.79 million.AUQ
Q1 2026 TU21 Dec 2025 - Revenue surged on first full-year copper sales, but losses increased amid higher costs.AUQ
H2 20251 Oct 2025 - Production and exploration advanced, cash position strengthened, and key licenses awaited.AUQ
Q4 2025 TU1 Oct 2025 - Alara Resources advances copper production, launches major capital raise, and targets growth in Oman.AUQ
AGM 202413 Jun 2025 - Commercial copper-gold production began in Oman, with revenue up but losses due to ramp-up costs.AUQ
H2 202413 Jun 2025 - Production and process improvements at Wash-hi Majaza mine drive higher copper output and efficiency.AUQ
Q1 2025 TU13 Jun 2025 - Copper-gold production launched in Oman, with new concessions and plant upgrades underway.AUQ
Q4 2024 TU13 Jun 2025