Achieved record half-year results: revenue up 64.6% year-over-year to $115.2m, adjusted EBITDA up 55.4% to $68.5m, and profit after tax up 58.4% to $42.7m, with EPS rising 58.4% to 156.38 US cents.
Gold sold increased 9.0% to 24,628oz at an average realized price of $4,615/oz, 50.3% higher than H1 2025.
Ore processed rose 10.1% to 498,331t, with the plant operating at 1Mtpa nameplate capacity; ore mined up 1.7%.
No lost-time injuries or reportable safety incidents recorded.
Financial highlights
Gross profit increased 49.0% to $59.9m; operating profit up 49.1% to $55.2m.
Net finance cost fell to $0.2m from $2.4m, aided by higher finance income and FX gains.
All-in sustaining cost (AISC) rose to $1,995/oz, up ~30% from FY 2025, mainly due to higher taxes, depreciation, and currency effects.
Cash generated from operations up 64.7% to $52.1m; net cash from operating activities up 19.7% to $36.5m.
Net assets increased 35.3% to $203.1m; total borrowings reduced by 23.8% to $31.4m; net debt stable at $19.3m.
Outlook and guidance
On track to meet full-year production guidance of 52-55Koz.
Ongoing review and technical work to increase processing capacity to 2.0-2.5Mtpa, with an update expected by year-end.
Teren-Sai project progressing toward production license, with further updates expected in Q4 2026.
Latest events from AltynGold
- Gold output and revenue surged, with full-year guidance reaffirmed and plant at full capacity.ALTN
Q2 2026 TU - Record revenue and profit, reduced debt, and strong growth outlook driven by mine expansion.ALTN
H2 2025 - Profitability and gold output soared in H1 2024, driven by higher grades and lower costs.ALTN
H1 2024 - Record revenue, profit, and capacity expansion set the stage for 60% gold output growth in 2025.ALTN
H2 2024 - Record H1 2025 profits and 44% gold output growth achieved after plant expansion.ALTN
H1 2025