13 Aug, 2026Executive summary
Achieved H1 2026 gold production of approximately 9,000 oz, at the upper end of guidance, with Nalunaq mine ramping up and processed head grades averaging 19.8–20 g/t.
Commissioned Phase 2 flotation circuit at Nalunaq in June 2026, achieving up to 90% recovery rates and seamless integration with Phase 1.
Largest exploration and development program underway, including significant drilling at Ilua Pegmatite, Naalakk/Nanoq, Minturn, and Maarmorilik.
Transitioned to the Main Market of the London Stock Exchange on July 31, 2026, enhancing access to international capital markets.
Strategic focus on developing Nalunaq, Maarmorilik, and Naalakk/Nanoq, each with growth potential in resources and production.
Financial highlights
H1 2026 revenue reached CAD 56.2 million (C$56.2M), up from CAD 3.4 million year-over-year, with gold sales of 8,610 oz at an average price of US$4,696/oz.
Gross profit was CAD 34.9 million, operating profit before exploration expenses CAD 17.8 million, and net income CAD 13.6 million, a significant improvement over H1 2025.
Operating cash flow of CAD 20.4 million in H1 2026, with a period-end cash balance of CAD 28.5 million.
Total assets increased to CAD 426.8 million, with shareholders’ equity at CAD 294.6 million as of June 30, 2026.
Ended Q2 with CAD 28.5 million in cash and access to a further CAD 18.5 million in undrawn facilities.
Outlook and guidance
Confident in delivering on full-year guidance, targeting FY2026 gold production of 25–35 koz, with ongoing ramp-up at Nalunaq and continued high grades.
Targeting annual plant throughput of 100,000 tons, with studies underway to increase capacity to 450 tons per day.
Maiden mineral resource for Naalakk/Nanoq expected following this year's drilling, pending logistics and assay results.
Focus on increasing liquidity and index eligibility through main market listing in London.
H2 2026 focus on ramping up mining and processing at Nalunaq, optimizing flotation circuit, and advancing exploration at Nanoq, Minturn, and within the Gardaq JV.
Latest events from Amaroq
- Greenland mining operations expand with strong Q1, major exploration, and LSE main market move.AMRQ
Precious Metals & Critical Minerals Hybrid Conference - Five-year plan drives gold, zinc, and critical minerals growth with strong financial performance.AMRQ
Capital Markets Update 2026 - Strong Q1 2026 results with gold output, revenue, and exploration plans exceeding expectations.AMRQ
Q1 2026 - Strong gold production, high-grade exploration results, and robust liquidity drive growth.AMRQ
Corporate presentation - 2026 gold output guided at 25–35koz, with strong 2025 results and major financing advances.AMRQ
Q4 2025 - Gold resource estimate rises 51% to 484Koz, supporting longer mine life and future growth.AMRQ
Corporate presentation - High-grade gold and copper confirmed at Nanoq, supporting major expansion and resource drilling in 2026.AMRQ
Status Update - Gold production starts in October, with accelerated growth, exploration, and clean energy focus.AMRQ
CMD 2024 - First gold pour, 51% resource boost, and $124M+ raised highlight a pivotal 2024.AMRQ
Q4 2024