Anglo Asian Mining (AAZ) H1 2026 earnings summary
Event summary combining transcript, slides, and related documents.
H1 2026 earnings summary
21 Sep, 2026Executive summary
Achieved record copper production of 8,840 tonnes in H1 2026, up from 1,188 tonnes year-over-year, with strong contributions from new Gilar and Demirli mines, marking the first full period as a multi-asset producer.
Gold and silver production also increased, with 12,329 ounces of gold and 92,855 ounces of silver produced.
Revenue surged to $141.2 million from $40.9 million year-over-year, with profit before tax rising to $68.5 million from $7.1 million.
Net cash from operating activities reached $78.5 million, supporting a net cash position of $57.7 million at period end.
Interim dividend of 6 US cents per share declared, reflecting strong cash generation and commitment to shareholder returns.
Financial highlights
Revenue increased to $141.2 million (H1 2025: $40.9 million), up 245% year-over-year, driven by higher copper and gold sales and prices.
Profit before tax rose to $68.5 million (H1 2025: $7.1 million), with profit after tax at $46.1 million (H1 2025: $4.7 million).
Net cash position improved to $57.7 million from $2.6 million at year-end 2025.
Operating cash flow was $78.5 million, up from $11.4 million year-over-year.
All-in-sustaining cost (AISC): Gold $1,224/oz, Copper $5,158/tonne.
Outlook and guidance
Copper and silver production guidance maintained; gold guidance slightly reduced to 26,000–30,000 ounces due to lower recoveries at Gilar.
2026 production guidance: copper 20,000–25,000 tonnes, gold 26,000–30,000 ounces, silver 170,000–210,000 ounces.
Reduced AISC copper guidance to $6,000–$7,000 per tonne.
Demirli mine expected to reach steady-state production in Q4 2026.
Xarxar and Garadag feasibility studies progressing, with production targeted for 2028–2029.
Latest events from Anglo Asian Mining
- Strong 2025 results and new mines drive growth toward 50,000 tpa copper target by 2030.AAZ
AGM 2026 presentation - 2025 saw a return to profitability and record output, with 2026 set for further production growth.AAZ
H2 2025 - On track to become a major copper producer with new mines, strong ESG, and disciplined growth.AAZ
AGM 2025 presentation - Targeting 36,000 tonnes of copper annually, leveraging vast resources and new mine developments.AAZ
Corporate presentation - 2024 saw lower revenue and output, but 2025 guidance signals strong production growth.AAZ
H2 2024 - Production and revenue fell sharply in H1 2024, but full operations are set to resume.AAZ
H1 2024 - H1 2025 saw a return to profit, strong revenue growth, and new copper mine production.AAZ
H1 2025 - Record Q3 copper output and strong 2025 guidance signal a positive financial turnaround.AAZ
Trading update