Mining Forum Americas 2026
Logotype for Asante Gold Corporation

Asante Gold (ASE) Mining Forum Americas 2026 summary

Event summary combining transcript, slides, and related documents.

Logotype for Asante Gold Corporation

Mining Forum Americas 2026 summary

12 Oct, 2026

Asset base and operating footprint

  • Two operating mines, Chirano and Bibiani, span a contiguous 83 km corridor reunited within the past three years after more than 100 years apart.

  • Asset base exceeds 6.5 million oz, with 2.8 million oz of reserves and a stated seven-year mine life; the land package is considered underexplored.

  • Chirano has 3.6 Mtpa milling capacity, five underground mines and open pits; Bibiani has a large open pit and processing facility.

  • Ghana is Africa’s largest gold producer, with gold accounting for 17% of GDP.

Chirano exploration and productivity

  • A six-month exploration program in late 2025 added about three years of mine life in a recently released PEA; exploration continues underground and at surface.

  • Drilling between Mamnao and Sariehu is identifying mineralization between the structures; drilling has yet to reach the higher-grade zones.

  • Management aims to lift underground productivity, accelerate declines into higher-grade areas and improve equipment efficiency over the next 6–12 months.

  • Kolua began mining in March 2026 with an initial three-month life and 10,000–15,000 t/month of oxide feed; follow-up drilling and grade control added another three months.

  • Step-outs have extended the Kolua mineralized zone from 300 m to about 1,000 m; similar extensions are being pursued at shallow Mamnao.

Bibiani mine planning

  • A January pit-wall failure covered much of the planned 2026 ore; waste removal was expected to finish around November 2026, while the ore delivery schedule was met.

  • Oxide resources in Cuts 5 and 6, at about 1 g/t with better recovery through the Bibiani mill, could support surface mining and defer underground development.

  • The revised concept would shift the production profile from 70%–80% toward about 30% underground, extend open-pit life and defer underground mining for several years.

  • Two RC rigs began drilling gaps in Cut 5; deeper drilling has returned strong results and supports management’s view of orebody continuity.

  • Russell Pit helped meet the 2026 ore schedule; future underground development may also access potential south of the pit.