Investor presentation
Logotype for Aspire Mining Limited

Aspire Mining (AKM) Investor presentation summary

Event summary combining transcript, slides, and related documents.

Logotype for Aspire Mining Limited

Investor presentation summary

15 Oct, 2026

Project scale and economics

  • JORC Coal Resource 219.4 Mt; Coal Reserve 130.1 Mt ROM, including 97.9 Mt marketable reserve; FM36 fat coking coal.

  • Production target stages from 1.5 to 2.5 to 5.0 Mtpa ROM, with a forecast ~31-year operating life.

  • Updated model forecasts US$1,483.3m post-tax NPV10, US$230/t long-term coal price and US$80.4/t cash cost delivered to Zamiin-Uud.

  • Phase 1 pre-production infrastructure capital is US$61.2m versus US$214.8m in the previous study; figures are not like-for-like.

  • Production target and forecasts include Inferred Coal Resources, approximately 12% of scheduled ROM coal.

Construction and timeline

  • Site establishment and early works are underway; the CHPP and rail terminal EPC contract is executed, with hiring ahead of planned Q1 2027 pre-stripping.

  • CHPP detailed design reached 85% review after quarter-end; subcontractor mobilised and batching plant commissioned.

  • Erdenet Rail Terminal design reached 30% review; its statutory trackwork and infrastructure feasibility study was approved by the transport ministry.

  • First coal production and export are targeted for Q4 2027, subject to construction progress, funding and approvals.

Funding and infrastructure

  • A US$60m Mongolian OTC bond program was registered; US$9.56m was placed in five tranches by 9 September 2026, at 11.0–13.0% coupons and 12–36-month tenors.

  • Sinosure-backed vendor financing is structured to defer 60% of the US$69.9m EPC contract, approximately US$42m, subject to insurance confirmation.

  • The Murun–Uliastai Highway is planned as a Build-Operate-Transfer PPP; the draft agreement awaits cabinet approval, with project-level entities established.

  • The model assumes US$126m of Mongolian OTC bonds and US$42m of deferred EPC payments; funding amounts and timing are assumptions, not assurances.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Aspire Mining