Auric Mining (AWJ) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
13 Nov, 2026Integrated development
Munda open-pit plan: 2.77Mt at 1.75 g/t over 2.7 years; 141koz recovered over 56 months at 25–40kozpa, with 89.5% recovery.
At A$5,750/oz, the integrated study estimates A$437m LOM EBITDA, AISC of A$2,843/oz and a 2.3-year payback; pre-production capital is A$138m and peak funding requirement A$145m.
The study covers 155koz of Munda’s 191koz MRE; mineralisation remains open along strike and at depth, with ~90,000m of grade-control drilling underway.
Open-pit mining is targeted for Q4 2027, with Burbanks commissioning and first gold targeted for Q1 2028.
Processing platform
Burbanks is a 100%-owned, permitted brownfield facility with an existing 180ktpa CIL plant and plans for a 600ktpa circuit, scalable to ~1.2Mtpa.
Existing power, water, road access and tailings infrastructure support redevelopment; Munda ore is planned to travel ~87km by sealed road to Burbanks.
The integrated plan targets regional feed beyond Munda, including Union Jack, Lindsays and Iron Maiden; regional mill capacity is under pressure and projects are pursuing toll treatment.
Resource growth and acquisitions
The portfolio spans seven gold projects over 628km²; pro forma resources are ~370koz, assuming completion of Iron Maiden and conversion of JORC resources.
Union Jack, 15km from Burbanks, has an Inferred resource of 3.12Mt at 1.02g/t for 102koz; drilling and resource upgrade work are planned ahead of mining studies.
Iron Maiden is 180km from Burbanks and has a historical JORC 2004 estimate of 1.4Mt at 1.5g/t for 69koz, 86% measured and indicated; acquisition completion is subject to due diligence.
Munda, Union Jack and Iron Maiden drilling targets resource growth, while regional exploration includes Spargoville and Higginsville.
Latest events from Auric Mining
- Burbanks-Munda advances toward 141koz production, with plant secured and Union Jack added.AWJ
Q3 2026 TU - Record profit and revenue in H1 2026, underpinned by strong gold output and cash flow.AWJ
H1 2026 - Munda resource upgraded 32%, Scoping Study projects A$437M EBITDA, cash at A$38M.AWJ
Q2 2026 TU - Record gold output and strong financials support growth and integration strategy.AWJ
Q1 2026 TU - Net profit after tax up 92% and revenue up 144% year-over-year, reflecting strong gold production.AWJ
H2 2025 - Revenue and profit surged on higher gold output, with major acquisitions set to boost 2025 growth.AWJ
H2 2024 - $4.46M revenue from Jeffreys Find, strong cash, and major project advances this quarter.AWJ
Q2 2024 TU - Returned to profitability with strong gold sales and self-funded operations.AWJ
H1 2024 - 6,295 ounces produced and $23.48M revenue from Jeffreys Find; Munda rights secured.AWJ
Q3 2024 TU