23 Nov, 2026Executive summary
2024 restarted oil and gas exploration and production following Phoenix’s acquisition; consolidated results included six months of Phoenix operations.
FY24 consolidated net loss was R$38.651 million, largely driven by a write-off of non-operating fixed assets during the Phoenix acquisition.
H2 production interventions temporarily curtailed output; operational improvements were expected to support higher oil production and resumed gas production in 2025.
A US$15 million agreement was signed to acquire Porto Carão and Barrinha assets in an equal partnership with Petro-Victory Energy, subject to ANP approval.
Financial highlights
FY24 consolidated net revenue was R$2.198 million, gross profit R$711 thousand, operating loss R$57.172 million and net loss R$38.651 million.
Operating expenses totaled R$57.883 million, including a R$53.971 million loss on disposal of fixed assets and R$3.528 million intangible amortization.
Income tax benefit was R$18.913 million, comprising R$18.971 million deferred benefit and R$58 thousand current expense.
Consolidated operating cash flow was R$28.382 million; investing outflow was R$223.859 million, financing inflow R$195.513 million and closing cash R$37 thousand.
Outlook and guidance
2025 production and results were expected to benefit from 2024 well interventions, planned oil-production increases and a gas restart.
Tanatau’s development plan was being prepared for ANP; planned investment supported initial 2025 production potential of 250 barrels/day, with 3.6 million barrels of oil in place.
A Periquito gas system commissioned in March 2025 had initial capacity up to 20,000 m³/day, expandable as production grows.
Q1 2025 planned investments: R$4M for ATP-PVE well AND-5 drilling, R$1.4M for Periquito gas commercialization, R$1.3M for a Brava-related Periquito signing installment and R$400K for engineering projects.
ATP planned to submit revised development plans to ANP, including investment in new production development wells.
Latest events from Azevedo & Travassos Energia
- Andorinha broadened the portfolio, while Q2 losses and ANP approvals shape production growth.AZTE3
Q2 2026 - Production rose 32% QoQ as expansion advanced amid funding and licensing risks.AZTE3
Q3 2025 - Revenue grew 72.3% QoQ as Periquito gas sales began and Andorinha drilling advanced.AZTE3
Q2 2025 - Q1 loss of R$4.5m as investment precedes expected H2 production growth.AZTE3
Q1 2025 - AND-3 restarted as losses, the Brava SPA dispute and funding needs pressured plans.AZTE3
Q3 2026 - Production rose 7.2% QoQ as losses narrowed and a proposed PVE deal awaited approval.AZTE3
Q1 2026 - Production advanced, while 4T25 posted a R$4.537m net loss.AZTE3