B2Gold (BTO) Q1 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2025 earnings summary
8 Jul, 2026Executive summary
Q1 2025 gold production reached 192,752 ounces, surpassing expectations across all operations, with strong performance after resolving operational issues at Fekola.
Goose Project construction is nearing completion, with first gold pour expected by end of Q2 2025 and ramp-up to commercial production in Q3.
Significant progress on permitting and development at Fekola regional in Mali, with government approvals advancing the project.
Gramalote feasibility study in Colombia is on track for completion by mid-2025, potentially leading to a development decision later in the year.
Strong liquidity with $330 million in cash and $174 million in working capital at quarter-end.
Financial highlights
Gold revenue for Q1 2025 was $532.1 million, up from $461.4 million in Q1 2024.
Adjusted earnings per share were $0.09, basic EPS $0.04, benefiting from strong gold prices.
Operating cash flow before working capital adjustments was $244 million ($0.19/share).
Goose project CapEx was $136 million in Q1 2025, with accelerated equipment purchases totaling about $60 million.
Net debt reduced after $400 million RCF repayment; $800 million undrawn on facility.
Outlook and guidance
2025 gold production guidance maintained at 970,000–1,075,000 ounces, with Goose and Fekola regional expected to drive growth.
Goose Project expected to produce 120,000–150,000 ounces in 2025, ramping to 300,000 ounces annually from 2026–2031.
Fekola regional exploitation permit expected within 30-60 days, with ore production to start after three months of pre-stripping.
Gramalote could commence development post-feasibility study, with potential production start around 2028-2029.
Antelope deposit at Otjikoto moving toward a construction decision in Q3 2025.
Latest events from B2Gold
- 2026 gold production guidance is 820,000–970,000 oz with strong financials and ESG focus.BTO
Corporate presentation27 Jul 2026 - Directors and auditor reappointed, growth projects advanced, and strong ESG focus maintained.BTO
AGM 20249 Jul 2026 - Q3 loss from Goose impairment; 2024 output on track, major projects advancing for 2025.BTO
Q3 20248 Jul 2026 - Record gold production expected in 2025, led by Goose Project and Fekola Complex expansions.BTO
Corporate presentation26 May 2026 - 2026 gold production guidance of 820,000–970,000 oz, with major growth and ESG initiatives.BTO
Corporate presentation12 May 2026 - Q1 2026 saw record gold output, strong cash flow, and robust capital returns.BTO
Q1 20267 May 2026 - Record 2025 revenue and strong mine performance set the stage for a transitional 2026.BTO
Q4 202513 Apr 2026 - 2026 gold production guidance up to 970,000 oz with strong ESG and exploration focus.BTO
Corporate presentation13 Apr 2026 - 2026 gold output forecast at 820–970 koz, with robust ESG, safety, and growth projects underway.BTO
Corporate presentation23 Mar 2026