Project progress and commitment

  • Bally's Chicago remains on track to open in early 2027, with construction ongoing and approximately 1,000 skilled tradespeople currently working on the permanent resort.

  • The project is expected to meet the $1.34 billion minimum capital commitment required under the agreement with the city.

  • Bally's continues to work closely with the city, labor, regulators, and the community to deliver a world-class integrated casino and resort.

Construction sequencing and capital allocation

  • In August, Bally's adjusted the sequencing of certain non-gaming development elements due to uncertainty from the legalization of video gaming terminals (VGTs) in Chicago.

  • This adjustment is described as a disciplined capital allocation, not a pause or stoppage, and aligns with the requirements and timelines of the host community agreement (HCA).

  • Bally's actions are intended to protect investor value and ensure all contractual obligations are met.

Investor relations and transparency

  • Bally's will send direct correspondence to shareholders inviting them to tour the construction site and observe progress firsthand.

  • The company emphasizes its ongoing commitment to transparency and engagement with investors and stakeholders.