BCI Minerals (BCI) H2 2025 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2025 earnings summary
26 May, 2026Executive summary
Transitioned into full-scale operations at Mardie, Australia's largest industrial salt project and third largest globally, marking a major milestone in company history.
Achieved significant construction progress, reaching 69% completion of the salt-first phase and pumping over 146 gigalitres of seawater, inundating 77% of pond surface area.
Secured key environmental approvals, completed major construction packages, and executed new offtake agreements covering 62% of forecast salt production for the first three years.
Successfully divested Iron Valley iron ore assets for $72.6 million, enhancing liquidity and strategic focus on industrial minerals.
Financial highlights
Cumulative Mardie expenditure reached $1,113M, with construction costs to date at $935M as of 30 June 2025.
Estimated construction cost to complete reduced to $508M, down from $874M in FY24.
Available funds at year-end were $753M, compared to $1,170M in FY24.
Received $26M initial and $34.1M deferred payments from Iron Valley sale, with an additional $12.5M due in July 2026.
Outlook and guidance
On schedule and within budget for Mardie Salt Project, with first salt on ship targeted for the quarter ending 31 December 2026.
FY26 focus on completing crystalliser construction, advancing salt wash plant, and progressing jetty dredging to de-risk pathway to first salt shipment.
Continued advancement of SOP pilot plant construction and FEED activities.
Latest events from BCI Minerals
- Project 77% complete, fully funded, net loss widens, Iron Valley sale and note conversion boost liquidity.BCI
H1 202626 May 2026 - 56% construction progress, $981M debt secured, Iron Valley divested for up to $72.6M.BCI
H1 202526 May 2026 - Mardie Project advances with robust funding, asset sales, and growing Asian market demand.BCI
H2 202426 May 2026 - Salt ramp-up and construction 81% complete; operations resumed and funding secured.BCI
Q3 2026 TU28 Apr 2026 - Salt project nears completion with secured sales, sustainable operations, and strong financials.BCI
Investor presentation17 Mar 2026 - 77% complete, fully funded, first salt shipment on track for December 2026.BCI
Q2 2026 TU3 Feb 2026 - Project surpasses 50% completion, fully funded, and targets first salt shipment by Q2 FY2027.BCI
Q1 2025 TU19 Jan 2026 - Mardie project reached 52% completion, operations began, and all AGM resolutions advanced to poll.BCI
AGM 202412 Jan 2026 - $981M financing secured, 56%+ complete, and first salt shipment targeted for Q2 FY27.BCI
Q2 20259 Jan 2026