3 Sep, 2025Market context and opportunity
Global LNG demand is rising, with structural supply shortages forecast from 2034, especially in Asia and Europe, driving the need for new supply sources.
Australian and Asian LNG prices trade at significant premiums to US Henry Hub, enhancing export economics for regional producers.
East Coast and Northern Territory gas supply deficits are projected from 2028, creating strong domestic market opportunities.
Strategic assets and resource base
Holds 100% ownership of the largest net acreage in the Beetaloo Basin, with high net revenue interest (~85%).
Beetaloo Basin is globally significant, estimated to hold over 200 TCF in-place; company controls 1.6 TCF (2C) and >47 TCFe (2U) of LNG-quality gas.
Carpentaria Project is pilot-ready with a 5 TCF resource and targets first production in 2026.
Project areas are located across the thickest section of stacked Velkerri Shale reservoirs, enabling up to 4x increase in net effective acres.
Project development and operations
Carpentaria Pilot Project has delineated >1,739 PJ (1.6 TCF) and achieved commercial flow rates; over 200 horizontal well locations identified in B Shale alone.
Carpentaria-5H is the longest horizontal shale well and largest hydraulic stimulation in Australia, with 67 stages and advanced logistics.
Carpentaria Gas Plant (42 TJ/d capacity) acquired and installation is imminent, with pipeline compression to support up to 25 TJ/d during pilot phase.
High-quality, low CO2 gas with elevated ethane content provides ~10% value uplift and is well-suited for blending with Ichthys LNG supply.
Latest events from Beetaloo Energy Australia
- Liquidity strengthened with $66.3M equity placement and $15.4M R&D refund; Carpentaria Gas Plant fully funded.BTL
Q1 2026 TU29 Apr 2026 - Carpentaria Pilot Project advanced, US assets sold, net loss narrowed, and cash reserves doubled.BTL
H2 20243 Apr 2026 - Carpentaria Pilot Project advanced to FID, with first gas sales targeted for late 2026.BTL
H2 20253 Apr 2026 - Carpentaria 5H to undergo Australia's largest fracking, with gas sales and expansion plans advancing.BTL
Emerging Growth Conference 8123 Dec 2025 - Beetaloo Basin development accelerates with new wells, gas sales, and LNG export ambitions.BTL
Emerging Growth Conference 7916 Dec 2025 - Record operational milestone at Carpentaria-5H and strong liquidity position support project progress.BTL
Q3 2025 TU21 Oct 2025 - Largest Beetaloo Basin frac, $35M raised, $9.08M loss, $6.12M US asset profit, strong liquidity.BTL
H1 202512 Sep 2025 - Liquidity strengthened and project milestones achieved ahead of 2026 production target.BTL
Q2 2025 TU30 Jul 2025 - C-5H stimulation and gas plant construction set stage for late 2025 gas sales launch.BTL