Executive summary

  • Progressed toward first pilot gas sales, with Carpentaria Gas Plant commissioning targeted for Q4 2026 and strong Carpentaria-5H flow-test results.

  • Launched Beetaloo Digital as a potential longer-term gas-to-power and data-centre market, while advancing Western Beetaloo seismic work.

Financial highlights

  • Received FY2025 R&D tax refund of $19.1 million plus $0.3 million interest, strengthening liquidity.

  • Quarter-end cash was $51.7 million; total available liquidity was $113.2 million, including $61.5 million in undrawn facilities.

  • Exercised 1,321,460 options at 24 cents per share, generating $317,150 cash.

Outlook and guidance

  • Carpentaria Gas Plant construction was nearing completion; commissioning and first pilot gas sales were targeted for Q4 2026.

  • Carpentaria-2H, -3H and -5H were expected to connect to the plant following completion of testing.

  • Beetaloo Digital concept and pre-FEED work will assess a potential integrated gas-to-power and data-centre development at Weddell.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Beetaloo Energy Australia