Big Digital Energy (BGDE) Q3 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 earnings summary
6 Nov, 2026Executive summary
Strategy shifted from powered sites toward AI/HPC development, while Bitcoin mining monetizes underused capacity; priorities include securing sites, customers, partners, and disciplined financing.
Hood County advanced into design and commercial discussions; Texas Load House acquired 30 acres, and a non-binding Tensor IQ LOI contemplates up to 17 MW for an AI/HPC campus.
Portfolio includes 169 MW of operating capacity and access to a Six Thirty AI development pipeline of nearly 600 MW.
Financial highlights
Q3 revenue was $8.7M, up 41% QoQ; gross profit was $4.5M versus $8.6M in Q3 2025, and operating loss was $5.5M versus operating income of $1.6M.
Net loss was $6.5M versus net income of $0.3M in Q3 2025; basic and diluted loss per share was $1.13. Adjusted EBITDA loss was $3.4M versus income of $2.7M.
Energy management revenue was $6.1M, up 132% QoQ; digital colocation revenue was $2.4M, down 30%; digital assets mining revenue was $0.2M, up 374%.
Cash was $3.1M at Sept. 30 versus $16.3M at June 30; the decline was primarily driven by the approximately $10M Hood County acquisition. Stockholders’ equity was $8.5M versus $12.4M.
Average monthly operating cash burn fell to $850K in Q3 from $3.4M in H1 2026; the improvement pace accelerated 50% from the start to the close of Q3.
Outlook and guidance
Target is cash-basis break-even by year-end; management also expects positive operating cash flow in Q1 2027.
Management expects to execute a Hood County lease by Q4-end; initial availability is targeted for Q2 2027, with timing subject to change.
Priorities include converting frameworks into definitive agreements, securing customers and financing, forming commercial relationships, and bringing additional powered infrastructure under control.
Hood County’s 111 MW expansion path is subject to ERCOT validation; a load study was approved to reach 74 MW, with additional capacity potentially supplied by behind-the-meter generation.
Latest events from Big Digital Energy
- 442,899 debt-exchange shares registered for resale as capacity shifts toward AI/HPC.BGDE
Registration filing - Six shareholder votes underpin a shift toward power-backed digital infrastructure and expanded financing capacity.BGDE
Proxy filing - Shareholders face major dilution-related proposals amid a pivot to AI and HPC infrastructure.BGDE
Proxy filing - Board seeks approval for director slate, share increases, equity plan, and key governance changes.BGDE
Proxy filing - Bitcoin miners are transforming into AI data center leaders, securing major deals and scaling fast.BGDE
H.C. Wainwright 28th Annual Global Investment Conference - Q2 revenue up 28% QoQ to $6.2M, with AI/HPC expansion and ongoing net losses.BGDE
Q2 2026 - Large equity offering poses significant dilution as the company pivots to digital infrastructure and AI.BGDE