Boss Energy (BOE) Market Day 2026 summary

Event summary combining transcript, slides, and related documents.

Logotype for Boss Energy Limited

Market Day 2026 summary

18 Sep, 2026

Strategic direction and operational transformation

  • Transitioned to a wide-spacing wellfield design, reducing wellfield infrastructure by 50% and all-in sustaining costs by AUD 30/lb, while increasing PLS head grade by 28%.

  • Developed a robust New Feasibility Study, enabling a shift from grade-focused to system-focused resource evaluation, especially for Gould's Dam and Jason's.

  • Positioned Honeymoon as a central production hub, integrating Gould's Dam and Jason's deposits for scalable, low-capital growth.

  • Aspires to ramp up production to 2.5Mlbs U3O8 per year at an AISC of A$65/lb by the early 2030s, significantly lowering unit costs and extending mine life.

  • Enhanced technical and operational capacity with a new, globally experienced team and board renewal.

Operational performance and optimisation

  • Honeymoon operation restarted in April 2024, achieving commercial production in January 2025, with 1.41Mlbs produced in FY26.

  • Ongoing plant debottlenecking and staged upgrades aim to lift water treatment capacity and support higher production rates.

  • Continuous improvement initiatives target reagent optimisation, wellfield efficiency, and infrastructure reuse to further lower costs.

  • Safety culture and operational excellence are emphasized, with ISO 45001-aligned systems and direct leadership accountability.

  • Continuous improvement programs have reduced costs and increased recovery rates, with further initiatives planned.

Resource base and development pipeline

  • Combined mineral resource of 65.9Mlbs U3O8 across Honeymoon, Gould's Dam, and Jason's Deposit, with significant potential for further extension.

  • Gould's Dam and Jason's Deposit are considered amenable to wide-spaced ISR, with ongoing drilling and permitting to upgrade and expand resources.

  • FY27 delineation drilling programs at both satellite deposits aim to increase resource confidence and support future production.

  • Regional exploration pipeline targets new ISR-amenable discoveries within the Honeymoon catchment.

  • Development timeline targets production from Jason's Deposit by early 2030 and Gould's Dam by early 2031, subject to permitting and board decisions.