Brazilian Critical Minerals (BCM) Q4 2026 TU earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for Brazilian Critical Minerals Limited

Q4 2026 TU earnings summary

24 Jul, 2026

Executive summary

  • Bankable Feasibility Study (BFS) completed for the Ema Project, confirming a two-stage development with a 20-year mine life and significant rare earth oxide (TREO, MREO) production volumes.

  • Updated JORC 2012 Mineral Resource Estimate: 1.07 billion tonnes @ 732 ppm TREO, with Indicated Resource up 58% to 392 Mt, de-risking future development.

  • Collaboration agreement signed with Southern Alliance Mining to explore joint rare earth production and distribution opportunities.

  • Permitting milestones achieved, including approval of Final Exploration Reports by Brazil's National Mining Agency and ongoing environmental and trial mining license processes.

Financial highlights

  • Stage 1 capex: US$74M (includes US$19M for CO2 capture/storage); Stage 2 expansion: US$27M.

  • Post-tax NPV8: US$1.47B (Base Case); post-tax IRR: 105%; payback period: 6 months.

  • Operating cash cost (C1): US$8.84/kg TREO; all-in sustaining cost: US$13.02/kg TREO.

  • Annual revenue (Base Case): US$265M; total LOM revenue: US$5.44B; project post-tax net cashflow: US$3.37B.

  • Cash and cash equivalents at quarter end: A$4.4M.

Outlook and guidance

  • Front-End Engineering Design (FEED) program to commence in the September quarter.

  • Continued engagement with environmental authorities and offtake partners; selection of a corporate partner for debt financing underway.

  • Estimated quarters of funding available: 7.08, with total available funding of A$8.41M.