Brightstar Resources (BTR) RIU Explorers Conference 2026 summary

Event summary combining transcript, slides, and related documents.

Logotype for Brightstar Resources Limited

RIU Explorers Conference 2026 summary

18 Feb, 2026

Strategic growth and project portfolio

  • Transitioned from a small explorer to a 4-million-ounce resource base with two operating mines and 140 employees in three years.

  • Focused on two hubs: Goldfields and Sandstone, both on granted mining leases with strong infrastructure and operational synergies.

  • Growth driven by targeted M&A and exploration, aiming for all projects to become producing mines in the near term.

  • Owner-operator model covers all mining functions, with significant investment in building internal systems and processes.

  • Portfolio assembled from acquisitions of underexplored assets, with potential to expand resources beyond current estimates.

Goldfields Hub development and economics

  • Definitive feasibility study (DFS) released, outlining a 6-year mine life producing over 75,000 ounces per year.

  • Projected to generate over AUD 1.5 billion in free cash flow and nearly AUD 1 billion NPV at current gold prices.

  • Fully funded for construction, with FID targeted for March and first gold pour expected by May/June next year.

  • Mill designed for 1.5Mtpa with embedded expansion to 2.5Mtpa, allowing for future production increases.

  • Production model simplifies operations to one open pit and one underground mine running concurrently.

Sandstone Hub opportunity and timeline

  • Sandstone holds 2.5 million ounces, mostly near surface, with significant upside from ongoing drilling.

  • Four rigs active, with resource upgrade and pre-feasibility study due mid-year; aiming for FID by end of next year.

  • Potential to develop into a 180,000+ ounce per annum operation for 10–15 years with a 5Mtpa mill.

  • Project benefits from strong infrastructure, including highway and gas pipeline access.

  • Funding for Sandstone’s build expected from Goldfields’ free cash flow, targeting construction start in 2028.