Executive summary

  • Advanced the Marillana Project with MinRes under the agreed Indicative Development Proposal, including ongoing technical, environmental, and social consultation work.

  • Joint venture with MinRes and Polaris for Marillana and Ophthalmia projects, with Polaris holding a 50% interest in Marillana.

  • No mining production or development activities were undertaken during the quarter.

Project activities

  • Confirmatory technical and due diligence studies for Marillana completed, indicating enhanced yields and product quality above 61.5% Fe.

  • Sinter testwork shows Marillana Fines can substitute for other Australian fines in Chinese steel mill blends.

  • Environmental management, water, and greenhouse gas plans updated; ongoing ecological and hydrological monitoring.

  • Social Surrounds consultation with Traditional Owners ongoing, as required by updated Western Australian legislation.

  • Infrastructure solution for Marillana being developed with MinRes, Hancock, and Roy Hill, including port capacity at Port Hedland's Stanley Point Berth 3.

  • Heritage survey completed at Duck Creek East; findings pending review.

Financial highlights

  • Consolidated cash position at 30 June 2026 was HK$3.9 million.

  • Net cash used in operating activities for the quarter was HK$4.1 million; year-to-date HK$20.1 million.

  • Net cash from financing activities was HK$5.2 million for the quarter; year-to-date HK$18.8 million.

  • Payments to related parties totaled HK$1.2 million for executive and non-executive directors' remuneration.