Cabral Gold (CBR) Corporate presentation summary
Event summary combining transcript, slides, and related documents.
Corporate presentation summary
17 Apr, 2026Project overview and development status
Cuiú Cuiú gold district in Brazil has district-scale potential with near-term production targeted for Q4 2026 from a Phase 1 starter operation focused on gold-in-oxide resources.
Construction of the Phase 1 heap leach project is 54% complete, with 71% of project costs committed and commissioning scheduled for Q3 2026.
A US$45M gold loan closed in November 2025 fully funds Stage 1 construction; first gold pour expected Q4 2026.
Full mining license (LP) granted in March 2026, significantly de-risking both Phase 1 and future Phase 2 hard rock development.
Resource base and exploration upside
Indicated resources: 12.29Mt @ 1.14 g/t gold (450,200oz) primary, 13.56Mt @ 0.50 g/t gold (216,182oz) oxide; Inferred: 13.63Mt @ 1.04 g/t gold (455,100oz) primary, 6.40Mt @ 0.34 g/t gold (70,569oz) oxide.
Five gold-in-oxide blankets identified (Central, MG, Machichie, PDM, Jerimum Cima) with 216,182oz Indicated and 70,569oz Inferred resources.
Four recent hard rock discoveries (PDM, Machichie Main, Jerimum Cima, Machichie NE) show high-grade intercepts, e.g., 9.5m @ 87.4 g/t gold at Jerimum Cima.
Over 50 peripheral targets identified, with ongoing drilling at MG, Jerimum Cima, and Mutum to expand the global resource.
Economic highlights and operational plan
July 2025 PFS: after-tax IRR of 78%, NPV5 of US$74M at $2,500/oz gold, capex US$37.7M, payback in 10 months, AISC US$1,210/oz.
Phase 1 targets 113,155oz gold production over 6.2 years, with 25,000oz/year in the first two years.
Simple heap leach processing route with average gold recovery of 88%; no crushing or grinding required.
Cash flow from Stage 1 will fund further drilling and expansion, aiming for a Stage 2 PEA on a larger hard rock resource in 2027.
Latest events from Cabral Gold
- Gold projects in Brazil advance with resource growth, high-grade finds, and near-term trial mining.CBR
2024 Precious Metals Summit Beaver Creek20 Jan 2026 - District-scale Brazilian gold project nears financing, with major resource growth and high-grade finds.CBR
Nordic Funds & Mines Conference 20258 Oct 2025 - Starter heap leach project targets near-term gold production with 78% IRR and major expansion potential.CBR
Corporate Presentation8 Oct 2025 - High-grade gold resources and a strong starter project position Cuiú Cuiú for rapid growth.CBR
Corporate Presentation23 Jun 2025 - Net loss of $7.28M in 2024 and funding uncertainty highlight significant going concern risk.CBR
Q4 20249 Jun 2025