Canyon Resources (CAY) H2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2026 earnings summary
30 Sep, 2026Executive summary
Advanced the Minim Martap Bauxite Project from development into construction, nearing production, with key infrastructure milestones achieved including rail and port logistics.
Increased strategic interests in Camrail (rail) and Terminal Bois du Port de Douala (port), strengthening logistics control.
Faced funding uncertainty as AFG Bank Cameroon suspended further drawdowns on a US$140M facility, prompting pursuit of alternative funding.
Received a conditional takeover offer from majority shareholder A2MP Investments FZCO, which was unanimously recommended to be rejected by the Board.
Leadership transition occurred with the CEO stepping down and a search for a permanent replacement underway.
Financial highlights
Net loss after tax of $9.48M for FY26, a significant improvement from $20.18M loss in FY25.
Cash at bank increased to $45.84M (FY25: $11.48M); net assets rose to $87.19M (FY25: $45.06M).
No dividends declared or paid.
Basic and diluted loss per share improved to (0.48) cents (FY25: (1.42) cents).
Share price at year-end was $0.09 (FY25: $0.25).
Outlook and guidance
Focus for FY27 is to resolve near-term funding, complete Stage 1 works, and deliver the maiden bauxite shipment.
Alumina refinery feasibility study progressing, with completion targeted for Q3 2026.
Offtake discussions ongoing, reflecting strong market interest.
Latest events from Canyon Resources
- Logistics milestones reached, strong liquidity, and takeover bid under review for project advancement.CAY
Q4 2026 TU - Mining operations and logistics for Minim Martap are on track, with full funding secured.CAY
Q3 2026 TU - Mining Licence secured, $24.7M raised, and net loss increased as Minim Martap advances.CAY
H2 2024 - Mining licence, funding, and DFS position Minim Martap for first ore in 2026; net loss rises on ramp-up.CAY
H2 2025 - Minim Martap advanced to mine development with improved loss, strong cash, and new funding.CAY
H1 2026 - Minim Martap targets premium bauxite production in Cameroon, with shipments starting Q4 2026.CAY
RIU Explorers Conference 2026 - Minim Martap Project on track for 2026 production, strong funding and infrastructure progress.CAY
Q2 2026 TU - World-class bauxite project advances with strong funding, robust economics, and Q2 2026 shipment target.CAY
Q1 2026 TU - Early 2026 production targeted, with high-grade reserves and strong project economics.CAY
Investor Update