Capricorn Metals (CMM) Diggers & Dealers Mining Forum 2026 summary
Event summary combining transcript, slides, and related documents.
Diggers & Dealers Mining Forum 2026 summary
4 Aug, 2026Strategic Overview and Growth Plans
Focus on building a high-margin, multi-decade gold business in Western Australia, with operations at Karlawinda and development at Mount Gibson, targeting production growth and operational scale.
Group ore reserves increased 33% to 5.24 million ounces, using conservative gold price assumptions, and mineral resources rose 29% to 8.66 million ounces.
Karlawinda has produced over AUD 1 billion in cash from 600,000 oz over five years, expanding to 150,000 oz per annum, with commissioning targeted for Q1 FY27.
Mount Gibson has grown to 3.7 million ounces of reserves, targeting 260,000 oz per annum over a 19-year mine life, with steady-state production confirmed by PFS.
Fully funded, debt-free position with over AUD 507 million in cash and equivalents as of June 2026, enabling internally funded growth and a Range 500 aspiration of 500,000 oz per annum within five years.
Financial Position and Operational Performance
Strong balance sheet with over AUD 507 million in cash and gold, no debt, and consistent cash build.
Karlawinda delivered a record 124,000 oz in FY 2026 and 30,000 oz in the June quarter, maintaining a 10-year mine life at expanded rates.
Maiden dividend returned, and processing expansion to 6.5 million tonnes per annum is in commissioning.
Mount Gibson's pre-production capital is AUD 474 million, with a pre-tax NPV of AUD 6.1 billion and AUD 12 billion in free cash flow at AUD 5,500 gold price.
Market capitalization of $6.2 billion as of July 2026, with institutional shareholders holding 54% and board/management 9%.
Project Development, Exploration, and Resource Growth
Mount Gibson's reserves have increased 2.5 times in three years, including maiden underground reserves and significant additions from Orion South.
Aggressive drilling and trade-off studies at MGGP and Lexington are expanding underground resource potential, with over 100 km of drilling planned in FY27.
Drilling at Orion South added significant open pit ounces; ore body remains open at depth and along strike.
Project design emphasizes simplicity, low costs, and robust plant and mining methods, with both KGP and MGGP positioned in the lowest quartile for operating costs.
High-grade underground feed is expected to grow, supporting future production increases and further growth potential at Lexington and other prospects.
Latest events from Capricorn Metals
- Annual gold output hit 123,589 ounces with strong cash flow and major expansion projects advancing.CMM
Q4 2026 TU - Reserves up 33% to 5.24 Moz; production outlook >400 koz pa, Range 500 targets 500 koz pa.CMM
Investor update - High-margin gold producer with >4Moz reserves, scaling to 300koz/year and strong cash flow.CMM
Investor presentation - Strong Q3 gold output, record cash flow, and project expansion keep FY26 guidance on track.CMM
Q3 2026 TU - Profit before tax nearly tripled year-over-year, supporting a maiden interim dividend and growth projects.CMM
H1 2026 - Quarterly gold output, record cash flow, and expansion progress support strong FY26 outlook.CMM
Q2 2026 TU - Record revenue, profit, and cash flow; debt-free with major resource and reserve growth.CMM
H2 2025 - Expanding gold projects drive record cash flow, reserve growth, and long-term value creation.CMM
Diggers & Dealers Mining Forum 2025 - Record revenue, profit, and cashflow support growth and development across key gold projects.CMM
H2 2024