Chalice Mining (CHN) Q1 2027 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2027 TU earnings summary
26 Oct, 2026Executive summary
Gonneville Definitive Feasibility Study (FS) remains on track for Q3 CY27; the eight-week full-flowsheet pilot is due to commence in November 2026.
Targeted Final Investment Decision (FID) remains H1 CY28, subject to FS completion, offtake agreements, funding and major environmental approvals.
Project development plan remains a two-stage, 5–14Mtpa open-pit mine, with no major changes to PFS scope, cost or schedule expected.
Financial highlights
Cash of $44.7M plus $8.2M in listed investments at 30 September 2026; total cash and listed investments were $53M.
Quarterly cash flow: $6.579M net operating outflow, $0.091M investing outflow and $0.063M financing outflow; closing cash was $44.706M.
Approximately $4M spent on Gonneville pre-development and approximately $1.5M on exploration during the quarter.
A $5M contingent payment is expected when Nyanzaga reaches commercial production; first production is expected in early CY27.
Outlook and guidance
FS completion targeted for Q3 CY27; offtake agreements targeted for H2 CY27 and funding and major environmental approvals for H1 CY28.
Following FID, an 18-month engineering and construction phase is expected, with first production targeted for early 2030.
Environmental Review Document and Public Environment Report submissions are on track for Q4 CY26; Mining Lease and infrastructure licence applications are expected in Q1 CY27.
Full project financing is expected after FS completion; funding strategy targets 60–70% of pre-production funding from export credit agencies, sovereign debt or grants, with the balance from streams, offtake-linked finance or strategic investment.
Latest events from Chalice Mining
- Kestrel reveals an open, high-grade copper-gold system, with follow-up drilling planned.CHN
Investor update - Gonneville targets H1 2028 FID, while palladium leverage and new drilling offer upside.CHN
Mining Forum Americas 2026 - Gonneville PFS confirms world-class, low-cost mine; FY26 loss $26.2m, strong cash, FS underway.CHN
H2 2026 - Advancing a world-class, low-cost PGM-nickel-copper project with strong growth and sustainability.CHN
Corporate presentation - Low-cost, long-life PGM-nickel-copper project targets FID in H1 2028 with strong growth upside.CHN
Resources Rising Stars Gold Coast Conference - Gonneville Project advances toward FID with robust cash reserves and pilot plant preparations.CHN
Q4 2026 TU - Advancing a world-class, lowest-cost PGM project with strong financials and growth upside.CHN
Noosa Mining Conference 2026 - Globally significant, low-cost PGM-Ni-Cu project with robust economics and major growth potential.CHN
Corporate presentation - Large-scale, low-cost palladium-nickel-copper project set for 2028 FID and strong financial returns.CHN
Investor presentation