CleanSpark (CLSK) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
10 Nov, 2026Strategy and power portfolio
Evolving from energy software and bitcoin mining toward energy and infrastructure compute, building on energy management, site development and industrial-scale operating experience.
2.1 GW of geographically diverse contracted power; portfolio grew from 520 MW at YE23 to 2.1 GW at 1H26, a stated increase of 600+%.
Texas entry includes Sealy (285 MW) and Brazoria (up to 600 MW); ERCOT issued conditional batch-zero classifications on 9/3/26, with differing baseload and studied-load designations by phase.
Strategy emphasizes energy expertise, interruptible offload, new acquisitions and organic expansions to accelerate AI/HPC development and maximize value per MW.
Sandersville lease and funding
Sandersville lease covers 175 MW of critical IT capacity, 250 gross MW, a 20-year base term and two 5-year extension options; lease is triple-net.
Base-term contract value is $6.6B, with ~ $330M average annual NOI; total contract value rises to $11.6B if both extensions are exercised.
Issued $2.276B of 7.875% senior secured notes due 2031; proceeds include project buildout, equity reimbursement and interest payments, with construction timeline stated as intact.
Total project cost is $2.480B including non-cash land appraisal value; cash-basis project cost is $2.373B, with financing at ~96% and ~92% loan-to-cost, respectively.
AI/HPC development platform
Development platform totals 2.11 GW of AI-suitable contracted power, including 340 MW leased, 1,475 MW under exclusivity and 885 MW of additional sites; 635 MW remains BTC-focused.
~75% of AI-suitable contracted power is leased or under exclusivity; additional sites span GA, TN and WY and may require land acquisition or conversion of interruptible to firm power.
Sealy energy availability is projected at 209 MW mid-2027, 52 MW mid-2028 and 24 MW mid-2029; Brazoria Phase I 300 MW is targeted for YE2027 and Phase II 300 MW for mid-2028.
Georgia site has 86 MW energized, ~5 EH/s operating hashrate and a completed 50 MW expansion; additional power is subject to transmission review by MEAG Power.
Latest events from CleanSpark
- AI data center investment is accelerating, fueled by real demand and strategic industry shifts.CLSK
H.C. Wainwright 28th Annual Global Investment Conference - Expanding AI/HPC infrastructure with 2 GW power, strong liquidity, and major long-term contracts.CLSK
Investor presentation - Signed a $6.6B, 20-year lease, pivoting to AI/HPC data centers amid steep losses and risks.CLSK
Q3 2026 - Secured a $6.6B, 20-year lease for 175 MW IT load, with Texas exclusivity and strong NOI margins.CLSK
Investor update - Revenue dropped 24.9% and net loss widened, but liquidity and infrastructure expansion remain strong.CLSK
Q2 2026 - Q1 revenue up 12% to $181.2M, net loss $378.7M, AI expansion and strong liquidity.CLSK
Q1 2026 - Vote on five directors and auditor ratification at the March 2026 virtual annual meeting.CLSK
Proxy Filing - Revenue up 129% to $104.1M, but $236.2M net loss from impairments; liquidity remains strong.CLSK
Q3 2024 - Disciplined growth, operational efficiency, and U.S. focus drive leadership in Bitcoin mining.CLSK
Jones Healthcare and Technology Innovation Conference