Companhia Energética de Brasília (CEBR5) Q3 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2025 earnings summary
24 Nov, 2026Executive summary
Q3 2025 consolidated revenue was R$123.1m, up 49.74% YoY, largely due to construction revenue recognized for the public-lighting concession.
Consolidated net income was R$53.6m, down 5.85% YoY, as higher income tax and social contribution expense offset improved gross profit and financial income.
9M consolidated net income reached R$177.3m versus R$160.2m in 9M24, while operating cash flow fell to R$60.0m from R$133.0m.
Financial highlights
Q3 net revenue R$123.1m versus R$82.2m YoY; gross profit R$50.2m, up 4.53%, and operating income before finance costs and taxes R$52.4m versus R$51.8m.
Q3 EBITDA was R$54.4m, with a 44.22% margin; both were broadly aligned with 3Q24 EBITDA of R$53.9m, though the reported prior-year margin was 65.60%.
Q3 financial result increased 7.41% YoY to R$22.7m, supported by higher returns on financial investments.
9M revenue was R$386.9m versus R$257.5m; gross profit was R$172.5m versus R$146.7m, and consolidated net income was R$177.3m versus R$160.2m.
9M parent-attributable net income was R$140.7m versus R$122.4m; basic EPS was R$1.8755 for ordinary and Class A shares and R$2.0630 for Class B shares.
Outlook and guidance
Public-lighting concession works and service delivery support construction revenue recognition; the contract asset reflects infrastructure services as performance obligations are completed.
The 3 MW shared-solar project with Terracap and STF was under construction, with ~R$10m estimated CAPEX and operations expected from February 2026.
A 10 MWp solar plant for ~400 public schools is planned to supply 60% of their electricity demand; ~R$40m CAPEX is fully funded by the Federal District Education Secretariat.
Public-lighting modernization targets 100% of the Federal District network by 2026, including replacement of conventional lamps with LEDs.
A November 2025 agreement with Terracap established a 4 MWp distributed-solar project, ~8.5 GWh annual generation potential and ~R$12m estimated CAPEX.
Latest events from Companhia Energética de Brasília
- Lighting-concession growth lifted revenue, while EBITDA and net income fell.CEBR5
Q4 2023 - Stable EBITDA, lower net income and major lighting and solar investment plans.CEBR5
Q4 2024 - Q2 earnings fell against prior-year hydrological concession revenue.CEBR5
Q2 2023 - Construction-led revenue surged, while earnings rose modestly and dividends remained substantial.CEBR5
Q4 2025 - Q3 earnings grew YoY as a 30-year public-lighting concession advanced.CEBR5
Q3 2023 - Q3 profit improved, but softer 9M results reflected revenue and concession-payment pressures.CEBR5
Q3 2024 - Concession construction revenue helped drive higher Q1 sales and profit.CEBR5
Q1 2025 - Revenue grew 15.39% YoY, while investment outflows weighed on cash generation.CEBR5
Q1 2023 - Revenue grew, but lower profit and EBITDA met a milestone concession transition and legal risks.CEBR5
Q1 2024