  • Q4 net revenue rose 14.1% YoY to R$2.614bn, EBITDA increased 11.4% to R$499.7m and net income rose 49.3% to R$302.1m; FY net revenue grew 8.7% to R$9.172bn and EBITDA 5.4% to R$1.945bn, while net income fell 15.3% to R$394m.

  • FY investment reached a record R$2.068bn, up 27.1%; DEC improved 10.6% to 8.65 hours, and collection reached 98.86%, its highest level in five years.

  • The Ceará distribution concession serves 184 municipalities; its term ends in May 2028, and a 30-year extension request remained under ANEEL review.

Financial highlights

  • Q4 net operating revenue was R$2.614bn, up 14.1%; excluding construction revenue, it was R$1.960bn, up 8.0%. FY net revenue reached R$9.172bn, up 8.7%, or R$7.214bn excluding construction revenue, up 3.9%.

  • Q4 EBITDA rose 11.4% to R$499.7m and EBIT 68.4% to R$477.3m; FY EBITDA rose 5.4% to R$1.945bn and EBIT 11.8% to R$1.379bn.

  • FY net financial expense widened 30.8% to R$965m; financial expenses rose 29.4% to R$1.263bn, mainly due to higher debt costs, CDI and legal-risk provisions.

  • Q4 and FY net income were R$302.1m, up 49.3%, and R$394m, down 15.3%, respectively; higher net financial expense weighed on the FY result.

  • Operating cash flow was R$1.899bn, investing cash outflow R$2.038bn and financing cash inflow R$108m; year-end cash was R$184m.

Outlook and guidance

  • The 2025–27 plan targets R$7.4bn of concession-area investment, 53% above the previous plan, prioritizing grid resilience, maintenance, modernization and service quality.

  • The plan includes 1,750 hires by 2027, over 170 km of high-voltage lines, 10,000 km of medium- and low-voltage network, and over 13,000 transformers.

  • A 30-year concession renewal request remained under ANEEL review after a director sought additional analysis; the Ministry approved the results plan in October 2025.

  • Renewal of the SUDENE incentive was denied; an administrative appeal was filed in January 2026.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Companhia Energética do Ceará