19 Nov, 2026Portfolio and strategy
Operations span Alaska and British Columbia, with Manh Choh at 30% ownership and Lucky Shot, Johnson Tract and Kitsault Valley each at 100%.
The direct ship ore model sends mined ore to off-site milling, avoiding an on-site mill and tailings facility while reducing footprint, permitting risk and upfront capital needs.
Five-year development target: 200,000 oz Au and 5M oz Ag; Manh Choh cash flow is positioned to support growth across the pipeline.
Manh Choh production
Kinross operates the mine and owns 70%; first gold pour was July 2024, following permitting in 18 months and construction and ramp-up in 2 years.
2025 production: 60,200 oz gold and 57,315 oz silver; AISC $1,616/oz sold; $102M cash distribution to the 30% owner.
Remaining hedge balance was nil as of July 1, 2026; approximate LOM cumulative cash target is $550M at $4,000 gold.
Development projects
Lucky Shot feasibility is underway; current measured and indicated resource is 105,620 oz Au at 14.5 g/t, with a 20,000m 2026-27 infill and expansion program targeting 400,000-500,000 oz Au.
Lucky Shot targets 40,000-50,000 oz Au annual production in 2028; planned 2026-27 spend is $50M-$60M to reach a production decision.
Johnson Tract initial assessment: ~1M oz AuEq at 9.4 g/t; at $4,000 gold, post-tax NPV5 $615.4M and IRR >60%, with $860/oz AuEq AISC, $213.6M initial capital and a 7-year LOM.
Johnson Tract’s 2026 work included road access to the portal site, equipment mobilization, camp winterization preparation, environmental and geotechnical studies, community outreach and FAST-41 permitting.
Latest events from Contango Silver & Gold
- High-grade Coleman results extend Lucky Shot as 2027 resource and feasibility work advance.CTGO
Investor update - Higher exploration spend and Manh Choh’s pit transition widened Q3 losses.CTGO
Q3 2026 - High-grade intercepts and advancing KM drilling support a 400,000-500,000 oz resource target.CTGO
Investor update - Aggressive growth targets and project execution are driving resource expansion and cash flow.CTGO
Mining Forum Americas 2026 - Fully funded for rapid growth, targeting 200,000 oz Au and 5M oz Ag annually via high-margin DSO assets.CTGO
Corporate presentation - Kitsault Valley’s indicated resource rose 93.1% to 89.55 Moz AgEq, with 2027 studies ahead.CTGO
Investor update - Major drilling and development milestones achieved safely and on budget, with key updates ahead.CTGO
Status update - High-margin, high-growth silver and gold producer leveraging DSO and strong cash flow for expansion.CTGO
Corporate presentation - Defense and tech demand, supply constraints, and policy shifts drive metals market transformation.CTGO
Fireside chat