H.C. Wainwright 28th Annual Global Investment Conference
Logotype for Dakota Gold Corporation

Dakota Gold (DC) H.C. Wainwright 28th Annual Global Investment Conference summary

Event summary combining transcript, slides, and related documents.

Logotype for Dakota Gold Corporation

H.C. Wainwright 28th Annual Global Investment Conference summary

14 Sep, 2026

Strategic positioning and project overview

  • Advancing a U.S.-based gold project in the Homestake District, South Dakota, with a focus on reducing geopolitical risk for investors.

  • Richmond Hill Gold Project is the primary asset, with 3,000 mineral acres and significant measured, indicated, and inferred resources.

  • Fully funded to shovel-ready stage with $99 million in treasury, minimizing dilution risk.

  • Project is located entirely on private land, streamlining permitting through state and county channels.

  • Agreements with Barrick secured key land and rights, providing a large, contiguous land package.

Project economics and development timeline

  • Initial Economic Assessment (IEA) at $2,350/oz gold shows $1.6 billion NPV; at current prices, NPV exceeds $4 billion.

  • Mine life projected at 17 years (measured/indicated), with potential extension to 28 years including inferred resources.

  • Production targeted at over 150,000 ounces per year at costs below $1,100/oz, with margins now exceeding $3,000/oz.

  • Pre-Feasibility Study (PFS) due Q4 this year, Feasibility Study next year, construction start in late 2028, and production in late 2029.

  • Trade-off studies underway to optimize throughput and sequencing, potentially increasing early production and cash flow.

Resource expansion and technical highlights

  • Over 1,000 drill holes inform the resource, with 350 new holes to be added for the PFS, increasing confidence and potential resource size.

  • Recent drilling focused on expanding northeast breccia zones, showing high recoveries (over 90%) and higher grades.

  • Metallurgical testing shows rapid leaching (30–40 days) and high recoveries, de-risking the project.

  • No significant processing challenges: no clay, deleterious elements, or preg-robbing, supporting reserve conversion.

  • Infrastructure advantages include existing roads, power, water rights, and proximity to skilled labor.