Develop Global (DVP) Q1 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2026 TU earnings summary
27 Oct, 2025Executive summary
Achieved key milestones at Woodlawn, with ramp-up on schedule and production set to reach nameplate capacity of 850ktpa by March 2026.
Updated Sulphur Springs DFS projects pre-tax free cashflow of A$1.5B, doubling previous forecasts, and a 76% increase in NPV to A$921M.
Mining Services Division secured a major contract extension worth ~A$130M with Bellevue Gold.
Group LTIFR was 0.0, with no material environmental or heritage incidents.
Financial highlights
Woodlawn revenue for the September quarter was A$19.7M from 7,962t of concentrate.
Mining Services external revenue was A$54M; internal revenue was A$17M.
Cash position at September 30, 2025, was A$203.8M.
Sulphur Springs DFS: LOM revenue A$3.42B, LOM free cashflow A$1.46B, IRR 59%, payback ~3 years.
Outlook and guidance
Woodlawn expected to reach steady-state production in March 2026, with potential to exceed planned tonnage rates.
Sulphur Springs advancing toward FID and construction, with all approvals in place and pre-development activities underway.
Anticipates further progress at both projects in the December quarter, leveraging strong commodity prices.
Latest events from Develop Global
- Record revenue, project milestones, and major funding drive strong growth outlook.DVP
Q4 2026 - Record production and strong margins achieved, with rapid mine development and robust outlook.DVP
Q3 2026 - Strong revenue growth and a return to profit, underpinned by project ramp-up and capital raises.DVP
H2 2025 - Woodlawn restart fully funded, Mining Services revenue up 117%, FY24 loss narrowed to $12m.DVP
H2 2024 - Revenue and profit surged on Woodlawn ramp-up and mining services growth; cash reserves strengthened.DVP
H1 2026 - Record revenue, project ramp-ups, and major contracts drive strong quarterly results.DVP
Q2 2026 TU - Revenue up 72% to $113m, net profit $1.17m, Woodlawn restart and financing secured.DVP
H1 2025 - Accelerating growth in copper, base metals, and mining services with strong institutional backing.DVP
RRS Gold Coast 2025 - Record revenue, first concentrate sales, and A$180m capital raise drive accelerated growth.DVP
Q4 2025 TU