27 Oct, 2026Executive summary
FY ended 30 Jun 1997 turnover was Rs 3,023.91 lacs, up 68% YoY; net profit rose to Rs 148.13 lacs from Rs 29.30 lacs, up 409% as reported.
Performance improved despite a severe recession in the cables industry and capital goods sector; alloy conductors remained the leading contributor to turnover and profitability.
Expansion and backward integration plans target higher conductor capacity and in-house aluminum/alloy wire rod production.
Financial highlights
Domestic sales were Rs 2,736.51 lacs vs Rs 1,801.15 lacs; export sales were Rs 287.40 lacs vs nil in FY96.
Profit before interest and depreciation was Rs 362.40 lacs; interest was Rs 152.77 lacs and depreciation Rs 50.75 lacs.
Profit before tax was Rs 158.88 lacs and profit after tax Rs 148.13 lacs; prior-year PAT was Rs 29.31 lacs in the accounts.
Reserves rose to Rs 412.87 lacs from Rs 236.07 lacs; share capital was Rs 900.80 lacs.
Outlook and guidance
Domestic institutional order book for the current FY stood at Rs 27.45 crore, alongside expected sales to industrial customers and dealers.
Proposed project plans AAAC capacity expansion from 1,900 to 12,700 MTpa and a 12,000 MTpa aluminum/alloy wire rod mill.
Project schedule targeted commercial production from Jan 1999 for one component and Apr 1999 for the other.
Management expected ISO 9002 certification for divisions by Nov 1997.
Latest events from Diamond Power Infrastructure
- Record Q2 revenue and H1 PAT above FY26, backed by net cash and a ₹3,735 crore order book.522163
Q2 26/27 - Profit rose as expansion and a Rs 90-crore order book positioned growth.522163
Q4 98/99 - Turnover and profit grew as aluminium rod expansion advanced alongside rising project commitments.522163
Q4 97/98 - Expansion lifted revenue and operating profit, while net profit fell and borrowing rose.522163
Q4 99/00 - Debt restructuring reset finances as power-sector demand promised growth and metal costs posed risk.522163
Q4 05/06 - Strong utility orders could not offset financing costs, delayed payments and delivery constraints.522163
Q4 02/03 - An 18-month period ended with a Rs. 2,075.64 lacs net loss and debt restructuring.522163
Q4 03/04 - Higher interest costs cut FY01 profit, while margin gains and a major TNEB order strengthened the outlook.522163
Q4 00/01 - Six-month profit returned, but debt stress and cash losses kept financial risk elevated.522163
Q4 04/05