Duos Technologies Group (DUOT) Q3 2026 earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for Duos Technologies Group Inc

Q3 2026 earnings summary

18 Nov, 2026

Executive summary

  • Strategic repositioning to modular compute-center colocation and infrastructure is complete; target distributed U.S. sites of 1–20 MW, with phased 5–10 MW builds tied to customer contracts.

  • Signed colocation value is ~ $560M, including a 10-year, 20 MW cloud agreement worth more than $400M; weighted average lease term is ~7 years.

  • Columbus began operations in October after more than 7 MW of infrastructure was installed in about 75 days; the hyperscale anchor deployment uses 2,304 NVIDIA B300 GPUs.

  • Powered, data-center-zoned land pipeline totals ~100 MW, with ~25 MW under contract and ~75 MW in active negotiations.

Financial highlights

  • Q3 2026 revenue was $10.50M, up 103% YoY; gross profit was $4.36M, up 156%.

  • Q3 operating expenses were $6.22M versus $2.6M YoY; operating loss was $1.86M versus $0.89M.

  • Q3 consolidated net income was $864K, while continuing operations recorded a $9.2M net loss after tax; Q3 Adjusted EBITDA was $493K.

  • 9M 2026 revenue was $18.82M, up 36% YoY; gross profit was $8.9M and operating loss was $4.98M.

  • 9M net income was $45.22M, driven by one-time investment-sale and GPUaaS deconsolidation gains.

Outlook and guidance

  • FY2026 revenue guidance was reaffirmed above $50M with positive full-year Adjusted EBITDA.

  • 2027 revenue outlook was reaffirmed at more than $160M; solid EBITDA growth is anticipated, with a full-year EBITDA range planned for the year-end 2026 call.

  • Q4 revenue is expected to be at least $30M; the V12 financial model projects $33M, including GPU compute services reported gross.

  • Q4 is expected to include a full quarter of hosting capacity contribution and continued Technology Solutions deliveries; a full quarter of Columbus site revenue was expected after October operations began.

  • The 20 MW cloud deployment is planned for Q2 2027; an additional Georgia site could begin operations as early as Q1 2027.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Duos Technologies Group