EAM Solar (EAM) Investor update summary

Event summary combining transcript, slides, and related documents.

Logotype for EAM Solar

Investor update summary

3 Nov, 2026

Corporate status

  • 9M'26 EBITDA was EUR 2.76m, mainly due to significant one-offs; a favorable Supreme Court of Cassation decision was secured and rebuilding began.

  • 142,320,980 shares outstanding; 5,090 direct shareholders, 98% Norwegian direct shareholders and 13% of shares held in nominee accounts.

  • Q4 priorities: pursue collection from Aveleos SA, start construction in November with equipment arriving from mid-November to mid-December, and review long-term strategy.

9M financial update

  • Booked EBITDA was EUR 2.7m, including EUR 3.2m of net non-recurring items; net cash flow was EUR 3.1m.

  • Net equity-issue proceeds were EUR 4.6m; EUR 2.88m cash received from tax refund and P31 bankruptcies; gross debt reduced by EUR 4.3m.

  • Equity ratio increased from 9.7% to 58%; profit after tax was EUR 2.05m vs. a EUR 0.56m loss in 9M'25.

  • Rebuild investment decision was EUR 1.6m excluding VAT.

Brundensini and Scardino rebuild

  • Fixed-price turnkey EPC contract totals EUR 1.603m plus VAT; all components ordered and 70% of investment cost payable in 2026.

  • Works expected to commence 16 November; Scardino goes offline first, followed by Brundensini two weeks later; plants expected online in February/March 2027, with testing in March/April.

  • Upgrades include Jinko Solar bifacial N-type modules, single-axis trackers, new fences and security systems, plus space for possible future development and batteries.

  • Annual power production expected to increase from 4,100 MWh to 7,200 MWh, a 75% rise.