EcoGraf (EGR) Q1 2027 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2027 TU earnings summary
25 Oct, 2026Executive summary
Epanko expansion engineering identified potential Stage 1 output growth of 20%, to 87,600tpa, while reducing estimated unit costs; 73,000tpa remains the debt-financing base case.
The vertically integrated plan spans Tanzanian graphite mining and shaping, European HFfree® purification, and battery-anode recycling; strategic equity and offtake discussions continued across these activities.
Quarter-end cash was A$1.767m; an A$4.727m capital raising completed in October to support financing, studies and exploration.
Financial highlights
Operating cash outflow was A$1.330m and investing cash outflow A$0.720m in the quarter; cash and cash equivalents ended at A$1.767m.
October capital raise totalled A$4.727m: A$3.552m via the Share Purchase Plan and A$1.175m via placement, at A$0.222 per share.
Evaluation and exploration expenditure was A$0.7m, primarily associated with Epanko activities.
Outlook and guidance
Further engineering studies, supported by EIB Technical Assistance, will assess the potential 87,600tpa case; updated NPV and IRR for that case have not been quantified.
EIB grant-funded workstreams provide up to €2m (A$3.2m) for technical, environmental, social and market studies covering Epanko expansion and integrated Midstream and Downstream pathways.
The current debt-financing case remains the 73,000tpa Updated BFS; the project is working toward financing completion and a Final Investment Decision.
Planned staged graphite concentrate capacity is 73ktpa at Stage 1, 130ktpa at Stage 2, 260ktpa at Stage 3 and 390ktpa at Stage 4.
Latest events from EcoGraf
- Epanko scale-up and HFfree expansion target integrated, lower-cost anode supply.EGR
Investor presentation - Epanko project advances, loss narrows, and strategic partnerships drive growth.EGR
H2 2026 - Vertically integrated graphite and battery anode business advancing scalable, low-cost global supply.EGR
Corporate presentation - Epanko financing, cost-competitive HFfree® process, and strategic partnerships drive growth.EGR
Q4 2026 TU - Epanko BFS confirms robust economics; financing and strategic partnerships advance amid positive outlook.EGR
Q3 2026 TU - Advanced graphite project funding and downstream expansion progress, with $11.2M cash on hand.EGR
Q4 2025 TU - Epanko project advances with 110% Proven Ore Reserve growth and US$105m debt mandate secured.EGR
H2 2024 - Half-year loss narrowed, Epanko project advanced, and graphite market outlook remains strong.EGR
H1 2026 - Epanko financing advances, downstream costs fall, and China’s export controls tighten supply chains.EGR
Q1 2026 TU