Eldorado Gold (ELD) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
2 Nov, 2026Investment case and growth outlook
2027E production of 886 koz GEO versus 519 koz in 2025, a 71% increase; presentation cites 2028 gold production growth of ~40%.
Portfolio spans six operations and projects across Canada, Greece and Türkiye, with 13+ years of average reserve life and 15% copper exposure.
2026 guidance: 425–475 koz total gold, 10–25M lb total copper and consolidated AISC of $1,975–$2,125/oz; guidance includes pre-commercial production at Skouries and Mcllvenna Bay.
Growth priorities include commissioning Skouries and Mcllvenna Bay, expanding Olympias and Lamaque, and advancing Perama Hill.
Project commissioning and development
Skouries produced first copper-gold concentrate on September 8; commercial production was targeted for late Q4 2026, with permanent grid power connected September 28.
Skouries project capital was revised to $1.425B, up $65M, plus $45M of previously guided growth capital; accelerated operational capital rose to $390M, up $95M.
Mcllvenna Bay produced first copper and zinc concentrates; commercial production was expected in late Q4 2026, with SAG and ball mill throughput increasing.
Mcllvenna Bay study assesses throughput expansion to 7,000 tpd from 4,900 tpd and a potential silver-lead circuit; development depends on evaluation, permits, engagement and an investment decision.
Perama Hill has 8.91Mt of proven and probable reserves at 3.18 g/t Au and targets ~100,000 oz annual production over an eight-year reserve life; feasibility work and consultations continue.
Operating performance and expansion
Q3 2026 production was 106,351 oz gold; consolidated total cash costs were $1,415/oz and AISC was $2,050/oz.
Lamaque Q3 production reached 52,748 oz; strong mill performance, higher head grade and recoveries, plus Ormaque contribution, supported results.
Kışladağ produced 22,713 oz in Q3; higher-grade ore was stacked, with benefits expected in late Q4 and 2027, while whole ore agglomeration ramp-up was expected in H1 2027.
Olympias Q3 production was 13,430 oz; the 650 ktpa expansion was ongoing, with final circuit tie-ins in Q1 2027 and nameplate ramp-up expected in H1 2027.
Lamaque is studying a staged mill expansion from 2,900 to 5,000 tpd; Olympias targets throughput growth of 30%, while Mcllvenna Bay expansion plans indicate 43% higher throughput.
Latest events from Eldorado Gold
- Higher gold prices lifted earnings as project ramp-ups pressured guidance and free cash flow.ELD
Q3 2026 - New mines, expansions and exploration underpin a forecast ~40% gold-production increase by 2028.ELD
Investor presentation - Gold and copper output surge and cash flow inflection in 2027 will boost shareholder returns.ELD
Mining Forum Americas 2026 - Skouries and Mcllvenna Bay ramp-up drives gold and copper growth, backed by strong ESG and financials.ELD
Investor presentation - ~40% gold growth by 2028, copper starts 2026, strong projects, robust ESG, and financial strength.ELD
Investor presentation - Strong gold prices and project advances drove higher Q2 earnings and future growth outlook.ELD
Q2 2026 - Production growth, new assets, and strong cash flow position the company for top sector performance.ELD
35th BMO Global Metals, Mining & Critical Minerals Conference - Merger forms a leading gold-copper producer with major assets entering production in 2026.ELD
M&A announcement - Record gold output and strong cash generation as Skouries construction advances.ELD
Q4 2024