Energy Resources of Australia (ERA) Q3 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 TU earnings summary
22 Oct, 2026Executive summary
Pit 3 capping reforecast adds ~14 months to the schedule; further rehabilitation cost increases of A$25m–A$95m in net present cost terms remain under review.
Progressive rehabilitation continued, with A$66m spent during the quarter; cash and other financial assets totalled A$439m at 30 September 2026.
Financial highlights
Rehabilitation expenditure was A$66m in the September quarter; no mining, production or development expenditure was incurred.
The revised Pit 3 capping methodology increases forecast completion costs; the impact is reflected in the rehabilitation provision at 30 June 2026.
Further Tranche 1A reforecast elements indicate potential additional rehabilitation costs of A$25m–A$95m in net present cost terms.
Outlook and guidance
Available financial resources are expected to support planned rehabilitation activities to approximately Q4 2027.
Finger filling capping is ahead of target; use of end tipping in the softest Pit 3 areas depends on trial completion and regulatory approvals.
A power purchase agreement starts in late Q4 2026 to support rehabilitation and maintain supply when existing power infrastructure is eventually demolished.
Latest events from Energy Resources of Australia
- Net loss widened to $214 million as rehabilitation costs and provisions increased sharply.ERA
H1 2026 - Net loss narrowed and rehabilitation advanced, but major funding and project risks persist.ERA
H2 2025 - Net loss improved to $35 million as rehabilitation and funding activities continued.ERA
H1 2025 - ERA launches $880m equity raise for Ranger rehabilitation, with Rio Tinto backing $760m.ERA
Investor Presentation - ERA seeks major equity funding for Ranger rehabilitation amid legal and financial pressures.ERA
Corporate Presentation - Net loss narrowed, but urgent funding is needed as cash may run out by early 2025 and legal action continues.ERA
H1 2024 - $43 million spent on Ranger rehabilitation; Jabiluka lease renewal denied, funding remains uncertain.ERA
Q2 2024 TU - Net loss narrowed sharply as ERA raised $766M for rehabilitation, but major risks persist.ERA
H2 2024