16 Oct, 2026

Economic assessment

  • Base case at $25/lb molybdenum and $5/lb copper: after-tax NPV8 of $745.1M, IRR of 16.1% and payback in production year 6.

  • At $33/lb molybdenum and $6.50/lb copper: after-tax NPV8 of $1,980.7M, IRR of 27.8% and payback in production year 4.

  • Initial capital is $686.8M, including $176.7M contingency; sustaining capital is $462.6M and closure cost is $86.5M.

  • AISC is $13.89/lb molybdenum, including copper credits; C1 cash cost is $10.24/lb.

  • Break-even is $18.50/lb molybdenum; projected revenue mix is 78% molybdenum and 22% copper.

Operating outlook and resources

  • PEA outlines a 34-year conventional open-pit mine and 25 Mtpa concentrator, processing 834.2 Mt of plant feed at a 1.31:1 waste-to-feed strip ratio.

  • Life-of-mine recovered production is estimated at 672.1 Mlb molybdenum and 947.2 Mlb copper; recoveries are 88.4% and 89.6%, respectively.

  • Updated resources include 407.1 Mt Measured and Indicated, containing 427.0 Mlb molybdenum and 553.7 Mlb copper; Inferred Resources total 596.2 Mt.

  • Inferred Resources account for 74% of PEA plant feed, including 16% scheduled during the six-year undiscounted payback period.

  • Conventional flotation is planned; mining fleet, drilling and blasting are assumed contractor-provided, with fleet capital included in operating costs.

Location and market position

  • Zuun Mod is 35 km from the Bayan Khundii Gold Mine, about 280 km from the Mongolia-China border railhead and within a 6,041-hectare license.

  • A power line built for Bayan Khundii is within 30 km; a new coal haul road is 35 km away, and the PEA assumes a third-party power purchase agreement.

  • Management cited molybdenum demand growth above 4% annually over five years, a structural supply deficit expected in 2026 and Asia accounting for nearly 65% of consumption.

  • Management said prices above $33/lb are supported by tight supply, rising Asian demand and limited new primary mine development.

  • Asian customers have shown long-term offtake interest; discussions continue with potential partners on offtake, financing and strategic partnerships.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Erdene Resource Development