Fenix Resources (FEX) Noosa Mining Conference 2026 summary
Event summary combining transcript, slides, and related documents.
Noosa Mining Conference 2026 summary
22 Jul, 2026Operational performance and growth
Achieved record quarterly shipments of 1.3 million tons in June 2026, up 33% from the previous quarter and 62% year-on-year, previously an annual figure.
FY26 iron ore sales reached 4.4 million tons, with guidance achieved and a 44% increase in cash to $81 million while funding expansion.
Integrated mining, haulage, and port operations under one management team, enhancing efficiency and scalability.
Annualised run rate exceeded 5 million tons per year by June 2026, targeting 6 million tons by FY28 and 10 million tons by FY31.
Confident in existing infrastructure's capacity to support up to 10 million tons annually.
Strategic projects and expansion plans
Weld Range Project secured with a 290 million ton resource and 30-year exclusive mining rights, underpinning long-term growth.
Published a scoping study in December 2025 outlining a pathway to 10 million tons of production.
Definitive Feasibility Study for Weld Range 10Mtpa expansion on track for late 2026.
Private haul road and technology enhancements planned to reduce logistics costs and support expansion.
Collaboration with Baowu and Sinosteel to support growth beyond FY28.
Infrastructure and integration
Fully integrated pit-to-port business model with 100% owned logistics and port operations.
Geraldton Port access secured to 2054, with on-wharf facilities and storage for growth.
New state-of-the-art workshop in Geraldton and scalable logistics to support 10Mtpa target.
Three operating mines and upgraded storage at Ruvidini siding.
Only integrated operator in the Mid-West region, supporting operational efficiency.
Latest events from Fenix Resources
- Record production and shipments, strong cash flow, and cost control support FY27 growth.FEX
Q4 2026 TU23 Jul 2026 - Production to reach 6 Mtpa by FY28, with robust resources and growth to 10 Mtpa targeted.FEX
Status Update8 Jul 2026 - FY27 guidance targets 4.7–5.3Mt iron ore sales with stable costs and growth focus.FEX
Guidance6 Jul 2026 - Record shipments and profits, cost discipline, and Weld Range deal drive long-term growth.FEX
H1 202626 May 2026 - Iron ore shipments hit 974k wmt, costs fell to A$70/wmt, and cash rose to A$86.3m.FEX
Q3 2026 TU21 May 2026 - Integrated pit-to-port model and 290Mt resource drive growth to 10Mtpa by 2031.FEX
Corporate presentation7 May 2026 - Iron Ridge margins remain strong as Fenix advances Shine and Beebyn-W11 projects for 2025 growth.FEX
Q1 2025 TU12 Feb 2026 - Record shipments and multi-mine growth offset lower prices, supporting strong cash flow and dividends.FEX
H2 202512 Feb 2026 - Record profit growth and major expansion projects set to boost production and future earnings.FEX
H2 202412 Feb 2026