Fermi (FRMI) Q3 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 earnings summary
12 Nov, 2026Executive summary
TensorWave’s lease was terminated; a November 10 non-binding LOI targets 600 MW of 2027 capacity for an investment-grade hyperscaler, with a $200 million prepayment and $15 million for early development. Definitive lease documentation remains pending.
A further $90 million steel and building-materials purchase agreement is being finalized; the customer pipeline could fill planned 2.2 GW of capacity if it converts to leases.
Project Matador has more than $1.6 billion invested, 6 GW of air permits, over 2 GW of generation equipment secured, and more than 15 million sq. ft. of data-center space contracted, under contract, or under option.
Financial highlights
September 30 cash and restricted cash totaled $315.5 million, including $286.3 million unrestricted and $29.2 million restricted.
Q3 net loss was $141.6 million, or $0.22 per share; G&A expense was $142.2 million.
Net PP&E was $1.67 billion; Q3 PP&E investment was $133.4 million and nine-month investment was $759.5 million.
Net debt was $958.4 million; Q3 operating cash use was $54.5 million and nine-month operating cash use was $110.6 million.
Outlook and guidance
Initial power for the 600 MW commitment is targeted for late Q2 or early Q3 2027; the customer expects its first building then, followed by up to eight buildings as available.
Sellable generation capacity is shown at 925 MW for 2027, 1,332 MW for 2028, and 2,000 MW for 2029; 600 MW is reserved for 2027.
Active investment-grade hyperscaler opportunities could cover planned 2.2 GW capacity; long-term development is presented at up to 17 GW, subject to customer agreements, permits, financing, interconnection and other conditions.
Incremental capex for the next 12 months is estimated at $2–$3 billion, subject to definitive leases and alignment with tenant deployment and power requirements.
Latest events from Fermi
- Powered-land plans advanced as shareholders rejected director nominees and approved auditor ratification.FRMI
AGM 2026 - Two director elections and EY ratification headline a proxy shaped by governance changes and Project Matador.FRMI
Proxy filing - Secured $6.5B anchor deal, doubled power capacity, and strengthened liquidity for rapid growth.FRMI
Q2 2026 - Massive 7,570-acre energy campus secures $1B funding and targets 17 GW scalable power.FRMI
Investor presentation - Board urges shareholders to reject Neugebauer's bid, citing risk to value and ongoing progress.FRMI
Proxy filing - Board urges shareholders to reject a disruptive Special Meeting and support ongoing strategic growth.FRMI
Proxy filing - Shareholders are urged to reject Neugebauer's proposals and support current board leadership.FRMI
Proxy filing - Shareholders are urged to support a Special Meeting to overhaul the Board and restore voting rights.FRMI
Proxy filing - Fermi 2.0 advances with new leadership, $189M net loss, $441M invested, and no revenue.FRMI
Q1 2026