Fervo Energy (FRVO) Q3 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 earnings summary
10 Nov, 2026Executive summary
Cape Station GeoBlock 1 began commercial operation Sept. 30, ahead of its contractual deadline, delivering 33 MW net; first power was Sept. 24 after ~23 months of construction.
A 15-year, take-or-pay Google PPA covers 396 MW across four 99 MW tranches; binding PPAs and other power-sale arrangements totaled 1,054 MW, representing $11.9B of backlog.
Unrestricted cash was $1.9B at quarter-end; resource potential reached 58.7 GW, including 8.4 GW at Cape Station.
Financial highlights
Q3 revenue was $116,000 versus $55,000 YoY; operating loss was $43.7M versus $13.7M, and consolidated net income was $11.7M.
Q3 net income included $15.4M interest income, an $11.8M non-cash swap gain and a $29.9M tax benefit; net loss attributable to common stockholders was $20.8M, or $0.07 per share.
G&A was $39.4M versus $27.4M in Q2, reflecting higher stock compensation, public-company costs and headcount growth.
Q3 CapEx was $256.7M versus $226.5M in Q2; 9M operating cash use was $55.4M and CapEx was $656.0M.
Outlook and guidance
Q4 CapEx is forecast at $450M-$500M; H2 CapEx at $700M-$750M, below prior guidance of $850M-$900M, with overall investment and commercial dates unchanged.
GeoBlocks 2 and 3 are on track for commercial operation by Jan. 1, 2027; 2027 revenue guidance remains $60M-$80M.
Cape Google 400 targets first power in mid-2028 and ~400 MW by year-end 2028; cumulative CapEx remains ~$2.2B through 2028.
Operating capacity targets are ~100 MW by early 2027 and ~500 MW cumulative by end-2028; installed capacity target is 1.1 GW by 2030.
Installed CapEx targets are $5,500/kW for GeoBlocks IV-XI and $3,000/kW long term; GeoBlocks I-III are expected to cost ~$7,000/kW.
Latest events from Fervo Energy
- Enhanced geothermal systems and major PPAs position the company for rapid, large-scale growth.FRVO
Investor presentation - $2.2B IPO, 500 MW under construction, $7.2B backlog, and 1.1 GW 2030 target.FRVO
Q2 2026 - $2.2B IPO, Google deal, and Cape Station drive geothermal growth and Q1 $31.8M net loss.FRVO
Q1 2026 - IPO funds to accelerate modular geothermal expansion, targeting U.S. firm power amid execution, regulatory risks.FRVO
Registration filing - IPO aims to raise $1.17B for modular geothermal expansion amid high demand and execution risks.FRVO
Registration filing - First-mover in scalable geothermal power, raising $1.17B to fund growth amid high execution risk.FRVO
Registration filing - First-mover in scalable geothermal power, targeting U.S. firm energy needs with strong growth pipeline.FRVO
Registration filing