28 Oct, 2026AGM proceedings and governance
Quorum was confirmed; formal business followed CEO presentations, with prior AGM minutes approved and financial reports and climate statements presented. Polls covered resolutions 1–8, with results due to the ASX later that day.
Sigrid Kaag, appointed a non-executive director in August 2026, stood for election; Andrew Forrest, Mark Barnaba, Penny Bingham-Hall and Larry Marshall stood for re-election.
Remuneration balances financial and non-financial measures, considers how results are achieved and aligns talent retention with long-term shareholder interests; directors undergo annual board and individual performance evaluations.
Shareholder approval was sought for CEO performance-rights participation; meeting materials disclosed maximum rights, measures and vesting conditions, with executive remuneration disclosures enhanced.
Directors emphasized independent judgment, execution discipline, accountability, safety and inclusion; outside board roles have no fixed cap and are assessed continually.
Financial and operational performance
FY2026 underlying EBITDA was $8.6bn, underlying NPAT $3.5bn and free cash flow $3.2bn; the $1.08 per-share dividend represented a 65% payout ratio, the eighth consecutive year at or above that level.
Iron ore shipments exceeded 200Mt for the first time; record exports and production were reported, with cumulative shipments reaching 2.5bn tonnes.
Iron Bridge magnetite production continued to ramp up; the Australian Shareholders Association noted a strong balance sheet.
~$40bn in projects have been executed since 2003; current projects were described as faster and lower-capital-intensity than Pilbara peers.
Energy and decarbonisation
A US$6.2bn decarbonisation program is advancing; generation and transmission execution is well advanced, with technical challenges solved and economics remaining the focus.
Green Grid plans include 1.5GW of solar, 900MW+ of wind, 2.4GW total renewable capacity, 5GWh of battery storage and 620km of transmission; over 1.3GW was operating or under construction, with 550km built.
A 20-year PPA with PLS Group’s Pilgangoora operation provides for at least 325GWh annually; the agreement marked the first Green Grid customer and supports a new long-term revenue stream.
A 240-tonne battery-electric haul truck was expected in the Pilbara within weeks, with hundreds more to follow; electric fleets could cut unit costs by $2–$4 per tonne, and 40% of the excavator fleet was targeted to be electric by December 2026.
Real Zero remains targeted for 2030, with ambitions to end fossil-fuel use by 2028; Solomon Solar Farm is expected to cost 40% less to build, and new technology nearly doubled the daily solar-foundation installation record.
Latest events from Fortescue
- Shipments held at 46.8Mt as CMRG talks drove a 3.9Mt sales gap and higher inventory.FMG
Q1 2027 TU - Record shipments, strong cash flow, and robust dividends amid major green investments.FMG
H2 2026 - Record shipments, strong cost control, and decarbonisation progress define FY26 results.FMG
Q4 2026 TU - Record shipments, strong cash flow, and major green energy investments drive growth.FMG
Q3 2026 TU - Record shipments, profit up 23%, strong cash flow, higher dividend, and decarbonisation progress.FMG
H1 2026 - Record first half shipments, strong cash flow, and ongoing decarbonisation initiatives.FMG
Q2 2026 TU - Record shipments, $3.4bn profit, and strong decarbonisation amid lower prices.FMG
H2 2025 - Net profit after tax hit US$5.7B, with 8% revenue growth and a 70% dividend payout.FMG
H2 2024 - Record shipments, but net profit fell 53% as prices dropped; green energy progress continued.FMG
H1 2025