Fortuna Mining (FVI) Q2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2026 earnings summary
12 Aug, 2026Executive summary
Delivered strong Q2 2026 operational and financial performance, generating $85.7 million in free cash flow and $200.8 million adjusted EBITDA, with a 63% margin and robust liquidity supporting ongoing growth projects.
Achieved Q2 gold equivalent production of 72,217 ounces and 145,089 ounces year-to-date, on track for annual guidance.
Advanced key growth projects: Séguéla plant expansion and Diamba Sud Gold Project, targeting 60% production growth by mid-2028 and over 200,000 oz/year gold production.
Returned $82.1 million to shareholders via buybacks in Q2; $106.6 million year-to-date, representing 41% of free cash flow.
Maintained strong liquidity with $756.7 million in cash and $435 million net cash at quarter end.
Financial highlights
Q2 sales reached $380 million; adjusted attributable net income was $75.5 million ($0.25/share); adjusted EBITDA was $200.8 million (63% margin).
First half sales totaled $661 million, adjusted EBITDA $420 million, and adjusted net income $186 million ($0.62/share).
Free cash flow from ongoing operations was $85.7 million in Q2 and $260 million for the first half.
Q2 average realized gold price was $4,447/oz, up 34% year-over-year; realized silver price was $75.22/oz, up 123%.
Q2 consolidated cash cost per gold equivalent ounce was $1,034; AISC was $2,157/oz, including $115/oz in one-time items.
Outlook and guidance
Annual production guidance remains on track at 281,000 to 305,000 GEO; Q2 expected to be peak AISC for the year, with costs trending lower in H2.
AISC projected to decline, especially at Lindero, with Q3 lower than Q2 and Q4 leveling off.
External factors such as royalties, Argentina macroeconomics, and diesel prices could impact full-year AISC.
Capital spending for Séguéla expansion ($109M) and Sunbird underground ($48M) to be spread through 2028 and early 2027, respectively.
Final investment decision for Diamba Sud Gold Project expected in H2 2026.
Latest events from Fortuna Mining
- Poised for 60% gold production growth by 2028, backed by strong assets and financials.FVI
Investor presentation - Robust growth, strong cash flow, and major project advances drive value across key mining assets.FVI
Investor presentation - Record sales, net income, and free cash flow, driven by higher gold prices and production.FVI
Q1 2026 - Strong gold growth, robust financials, and leading ESG drive expansion in key mining regions.FVI
Investor presentation - Advancing Séguéla and Diamba Sud to restore 500,000 oz gold output, backed by strong cash flow.FVI
Mining Forum Europe 2026 - Record 2025 results, robust growth pipeline, and leading ESG performance across core assets.FVI
Investor presentation - Record 2025 results and major project advances set the stage for continued growth in 2026.FVI
Investor presentation - Record free cash flow and strong production drive robust 2025 results and future growth.FVI
Q4 2025 - Record free cash flow, 44% sales growth, and strong margins drive portfolio optimization.FVI
Q1 2025