Frontier Energy (FHE) H2 2025 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2025 earnings summary
8 Mar, 2026Executive summary
Focused on developing the Waroona Renewable Energy Project in Western Australia, integrating a 120MWdc solar farm and 81.5MW battery, with key permits and approvals secured.
Secured a major grid connection and executed an Electricity Transfer Access Contract, enabling electricity sales into the SWIS.
Completed an updated Definitive Feasibility Study in January 2025, reflecting lower capital costs and updated electricity price forecasts.
Assigned 88.06 MW of certified reserve capacity for 2027-2028, with expected annual revenue of ~$32 million from capacity credits, fixed for five years.
Withdrew from CIS Tender 2 to pursue a more suitable application under CIS Tender 6.
Financial highlights
Net loss for the year ended 31 December 2025 was $5,167,709, including a $1,355,358 impairment of exploration and evaluation assets (2024: $18,122,872 loss).
Cash and cash equivalents at year-end were $5,587,807 (2024: $14,334,978).
Net assets increased to $84,795,932 (2024: $81,271,776).
Share price at year-end was $0.24, up from $0.12 in 2024.
No dividends declared or paid.
Outlook and guidance
Strategy remains to create a significant vertically integrated renewable energy company in Western Australia.
Will continue to pursue development of the Waroona Project and expansion opportunities.
Latest events from Frontier Energy
- Project remains on schedule, with financing and revenue certainty secured for critical energy expansion.FHE
Investor Update10 Dec 2025 - $18.1M net loss, major asset impairment, and Waroona Project advances with new funding.FHE
H2 20241 Dec 2025 - Half-year net loss narrowed to $210,593 as renewable project progress and asset sale boosted results.FHE
H1 20251 Dec 2025 - 88.06 MW capacity credits secured, guaranteeing $32M annual revenue and supporting project financing.FHE
Q3 2025 TU30 Oct 2025 - Strategic investor process advanced and Waroona Project remains on track for 2027 operations.FHE
Q2 2025 TU30 Jul 2025 - Development-ready 120MW solar and battery project offers strong returns and growth potential.FHE
Investor Presentation1 Jul 2025 - Waroona project targets WA's surging energy demand with a 120MW solar and 80MW battery facility.FHE
Investor Presentation1 Jul 2025 - Development-ready 120MW solar and 80MW battery project targets strong returns and rapid growth.FHE
Investor Presentation1 Jul 2025 - Updated DFS, strong cash position, and high WA energy prices support Frontier's project outlook.FHE
Q3 2024 TU13 Jun 2025