28 Oct, 2026Andacollo restart and production
Historical mine with 6M oz of resources: ~1.5M indicated and 4.5M inferred; prior operators produced over 1M oz, with peak output above 130,000 oz.
Restart capital estimated at $60M–$70M; management said financing is in place, with existing infrastructure including heap-leach pads and an ADR plant.
ADR plant refurbishment was targeted for completion by late November to mid-December 2026; the 20,000-ton/day replacement crusher from Mexico is the main commissioning gate.
Crusher disassembly and shipment to Chile are underway; the plant is permitted, with customs cited as a potential delay risk. Management hoped the project would be ready by end-March 2027.
Plan is to bring the crusher to site in early 2027, commission it, and begin stacking pads in Q2; gold production is targeted in 2027, with cyanide circulation on existing pads by late 2026 treated as upside, not base case.
Resource and strategic upside
Heap-leach metallurgy has a production history; management expects 70%–75% recovery and cited 300,000–400,000 oz previously defined in historical pads.
Resource is drilled to ~250 m; management sees potential to extend it at depth and grow through drilling, including high-grade zones and oxide copper near the property boundary.
About 90M tons containing 1.2M oz of gold have been drilled beyond the constrained pit boundary but are not included in the resource; mining access would require resolving the boundary with Teck.
Management wants to explore possible cooperation or an acquisition of Teck’s adjacent Carmen de Andacollo asset, conditional on an opportunity arising; it views the combined area as one large porphyry-related system.
Indiana exploration
Historical resource across Bondadosa and Flor de Espino is ~5M tons, ~330,000 oz of gold at 2.25 g/t and ~65,000 tons of copper at 1.3%; mineralization is open at depth and along strike.
Mapping and trenching identified additional north-south structures and disseminated mineralization; an aggressive drill program will test potential for a larger, bulk-mineable resource before a full production push.
Capital allocation is focused ~90% on Andacollo and 10% on Indiana; Indiana plans call for exploration and limited underground development, keeping cash burn minimal.
Latest events from Galantas Gold
- Andacollo restart and Indiana development anchor a two-asset gold-copper growth plan.GAL
Corporate presentation - Advancing two Chilean gold-copper projects toward production with strong resources and funding.GAL
Corporate presentation - Q2 2026 net loss of $4.69M, $100M raised, and major Chilean project expansions underway.GAL
Q2 2026 - Net loss increased, but cash and working capital improved; major financing and resource updates announced.GAL
Q1 2026 - Andacollo project in Chile targets late 2026 restart, major resource growth, and debt-backed financing.GAL
Precious Metals & Critical Minerals Virtual Investor Conference - Net loss widened to $8.5M in 2025, with improved cash and working capital but no recognized revenue.GAL
Q4 2025 - Q2 2024 saw a higher net loss, no revenue, and increased cash outflow amid ongoing operational risks.GAL
Q2 2024 - Net loss improved in Q3 2024, but cash and working capital positions weakened.GAL
Q3 2024 - Transitioning to multi-asset gold production in Chile with near-term growth and exploration upside.GAL
Corporate presentation