Global Lithium Resources (GL1) H2 2026 earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for Global Lithium Resources Limited

H2 2026 earnings summary

27 Oct, 2026

Executive summary

  • FY2026 advanced Manna toward development through a Native Title Mining Agreement, a 21-year mining lease, an optimized DFS, and strategic Lopal funding and offtake arrangements.

  • Post-year-end, the Manna-Nova Integration Study outlined a lower-capital development route; a proposed Titan scheme would provide shareholders A$1.15 per share, subject to conditions.

Financial highlights

  • FY2026 net loss was A$6.854m, versus A$3.846m in FY2025; loss included A$1.843m share-based payment expense and A$2.575m impairment expense.

  • Total income was A$1.071m versus A$1.768m; loss per share was A$0.026 versus A$0.015.

  • Cash and cash equivalents were A$26.231m at 30 June 2026, versus A$16.042m a year earlier; net cash used in operating activities was A$4.784m versus A$10.186m.

  • Total assets were A$171.248m and net assets A$169.943m at year-end; total liabilities were A$1.305m.

Outlook and guidance

  • FID for Manna was targeted for the December 2026 quarter; first DSO shipment was targeted for May 2027 and first spodumene concentrate for mid-2027.

  • Priorities include progressing funding and approvals, completing the Nova acquisition, and preparing for development; target timing remains subject to funding, logistics, execution and market conditions.

  • The Integration Study estimated a 13-year mine life and 2,684.3kt life-of-mine concentrate production, with average annual output of 257kt SC5.5 for the first seven years.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Global Lithium Resources