13 Jun, 2025Executive summary
Completed 6,261m RC drilling at Manna Lithium Project, confirming a 600m southwest extension with significant intercepts up to 21m @ 0.99% Li₂O.
Manna DFS metallurgical testwork finalized, achieving 78% lithia recovery; ore sorting trials show >97% spodumene recovery and >90% iron rejection.
All required Aboriginal Heritage Surveys and key land access approvals completed for Manna.
Significant corporate restructuring and cost reductions implemented due to lithium market downturn, including pausing parts of the Manna DFS and reducing board size.
Cash position of $21.5 million and listed equity investments of A$3.4 million as of 30 September 2024.
Financial highlights
Net cash outflow from operating activities was $5.17 million for the quarter, mainly due to exploration, DFS costs, and restructuring.
Cash and cash equivalents at quarter end were $21.5 million, with no debt.
Estimated quarters of funding available: 4.16, based on current cash burn.
Outlook and guidance
Expects to maintain sufficient funding to weather a prolonged lithium market downturn, with further cost reductions effective from December 2024 quarter.
Plans to resume full DFS and construction at Manna when market conditions improve.
Ongoing evaluation of multi-commodity exploration opportunities for additional value.
Latest events from Global Lithium Resources
- Returned to profitability and advanced lithium project milestones, boosting cash and strategic focus.GL1
H1 202615 Mar 2026 - Large-scale lithium project with strong economics and advanced permitting targets 2028 production.GL1
Investor presentation1 Mar 2026 - Manna Lithium Project advanced with key agreements; cash reserves rise to $21.46m after asset sale.GL1
Q1 2026 TU30 Oct 2025 - Net loss narrowed, Manna DFS advanced, and key agreements secured amid lithium market downturn.GL1
H2 202528 Sep 2025 - Progressed Manna DFS, cut costs, and secured 11.4 quarters of funding with $16M cash.GL1
Q4 2025 TU27 Jul 2025 - DFS activities resumed at Manna, with $17.5M cash and 13.5 quarters of funding available.GL1
Q3 2025 TU15 Jun 2025 - Net loss of $4.37M, Manna resource up 43%, and cost cuts amid lithium market weakness.GL1
H2 202413 Jun 2025 - Manna resource grows 43% to 51.6Mt, with DFS and key approvals on track for 2024.GL1
Investor Presentation13 Jun 2025 - Manna Lithium resource up 43% to 51.6Mt; DFS and permitting progress support 2025 growth.GL1
Q4 2024 TU13 Jun 2025